2649 E ARVIA ST 90065

Certificate Information: 2649 E ARVIA ST 90065

Application / Permit
20016-30000-02765
Plan Check / Job No.
B20WL00487
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
INTERIOR REMODEL TO EXISTING DUPLEX
Permit Issued
Issued on 2/14/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 5/25/2021

Permit Application Status History

Submitted 1/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 KAVIAN REFAHI
Corrections Issued 1/30/2020 KAVIAN REFAHI
Plan Check Approved 1/31/2020 VLADIMIR ARUTYUNYAN
Issued 2/14/2020 LADBS
Permit Finaled 5/24/2021 OSVALDO PARAMO

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/4/2020 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 5/4/2020 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/8/2020 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Corrections Issued OSVALDO PARAMO
Wood Frame 10/26/2020 Partial Inspection COREY HUPP
ELECTRICAL-Rough 1/6/2021 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 1/6/2021 Corrections Issued OSVALDO PARAMO
HVAC-Rough 1/11/2021 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 1/13/2021 Approved OSVALDO PARAMO
HVAC-Rough 1/13/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 1/13/2021 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 1/13/2021 Approved OSVALDO PARAMO
Wood Frame 1/13/2021 Approved OSVALDO PARAMO
Wood Frame 1/19/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 1/21/2021 Approved OSVALDO PARAMO
Insulation 1/21/2021 Approved OSVALDO PARAMO
Drywall Nailing 2/1/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 2/1/2021 Approved OSVALDO PARAMO
Final 5/13/2021 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/13/2021 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 5/13/2021 Approved OSVALDO PARAMO
Final 5/24/2021 Permit Finaled OSVALDO PARAMO