825 W DICKSON ST 90292

Certificate Information: 825 W DICKSON ST 90292

Application / Permit
20016-30000-02531
Plan Check / Job No.
B20WL00428
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel to (e) 2-story structure (SFD).
Permit Issued
Issued on 9/1/2020
Issuing Office
Metro
Current Status
Permit Finaled on 10/25/2021

Permit Application Status History

Submitted 1/28/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 TSE MING HUANG
Corrections Issued 3/16/2020 TSE MING HUANG
Quality Review Completed 3/31/2020 STANLEY RAAP
Building Plans Picked Up 4/14/2020 APPLICANT
Applicant returned to address corrections 6/25/2020 TSE MING HUANG
Plan Check Approved 8/21/2020 TSE MING HUANG
Issued 9/1/2020 APPLICANT
Permit Finaled 10/18/2021 JOHN TCHANG

Permit Application Clearance Information

Coastal Zone Cleared 4/20/2020 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 4/20/2020 DINAH GARIN
Miscellaneous Cleared 4/20/2020 LOUIS ORTEGA
Roof/Waste drainage to street Cleared 4/20/2020 DINAH GARIN
Sewer availability Cleared 4/20/2020 DINAH GARIN

Contact Information

Architect Poloukhine,, Michael; Lic. No.: C32850 3489 MAPLEWOOD AVENUE      LOS ANGELES, CA 90066
Engineer Shirley,, Peter Franklin; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/11/2020 No Access for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 9/11/2020 No Access for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 9/15/2020 Approved DAVID HEINE
Footing/Foundation/Slab 9/15/2020 Approved DAVID HEINE
Wood Frame 9/25/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 10/6/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Partial Approval DAVID HEINE
Final 11/9/2020 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 11/9/2020 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 11/9/2020 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 11/16/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Not Ready ENRIQUE MIRELES
Smoke Detectors 11/16/2020 Approved ENRIQUE MIRELES
Special/Order Compliance 11/16/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 11/16/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Partial Inspection KENNETH NAGLE
Insulation 11/20/2020 Approved KENNETH NAGLE
Insulation 11/23/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Approved ENRIQUE MIRELES
Wood Frame 12/1/2020 Approved ENRIQUE MIRELES
Drywall Nailing 12/3/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/3/2020 SGSOV Not Ready ENRIQUE MIRELES
Drywall Nailing 12/4/2020 Approved JOHNNY MIRANDA
Final 10/18/2021 Permit Finaled JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Approved JOHN TCHANG
SGSOV-Seismic Gas S/O Valve 10/19/2021 SGSOV Approved JOHN TCHANG