2650-2652 N LISCO PL 90046

Certificate Information: 2650-2652 N LISCO PL 90046

Application / Permit
20016-30000-02506
Plan Check / Job No.
B20WL00422
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLIG UNIT PER AB 494 & SB 229. PER WFPP
Permit Issued
Issued on 9/14/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2020 APPLICANT
Assigned to Plan Check Engineer 1/29/2020 ALFREDO JARA
Corrections Issued 1/31/2020 ALFREDO JARA
Applicant returned to address corrections 6/30/2020 ALFREDO JARA
Applicant returned to address corrections 7/14/2020 JAHANSHAH POURHASSAN
Plan Check Approved 7/24/2020 PARISA ZAHABI
Issued 9/14/2020 APPLICANT
Building Plans Picked Up 9/15/2020 APPLICANT
CofO in Progress 10/19/2022 BRIAN SULLIVAN
Permit Finaled 11/19/2022 DEROLD HAUFF
CofO Issued 11/19/2022 DEROLD HAUFF
Permit Finaled 11/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 6/23/2020 LIZZI BEDUYA
ZA Case Cleared 6/23/2020 LIZZI BEDUYA
Grading Pre-Inspection Cleared 6/30/2020 KIRK LINKLATER
Address approval Cleared 7/7/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 7/7/2020 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 7/7/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/7/2020 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/15/2020 Corrections Issued BRIAN SULLIVAN
Pre-Inspection 9/18/2020 No Access for Inspection BRAD BESCOS
Pre-Inspection 9/23/2020 Partial Inspection BRIAN SULLIVAN
Special/Order Compliance 9/23/2020 Approved BRAD BESCOS
ELECTRICAL-Rough 9/30/2020 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 9/30/2020 Not Ready for Inspection BRIAN SULLIVAN
Pre-Inspection 9/30/2020 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 10/6/2020 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 10/15/2020 Partial Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 11/2/2020 Partial Approval BRAD BESCOS
Pre-Inspection 11/2/2020 Not Ready for Inspection BRIAN SULLIVAN
Pre-Inspection 11/16/2020 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 11/24/2020 Not Ready for Inspection BRAD BESCOS
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Not Ready for Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 11/24/2020 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 12/9/2020 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 12/16/2020 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 12/24/2020 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 12/28/2020 Not Ready for Inspection BRIAN SULLIVAN
Pre-Inspection 1/6/2021 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 2/1/2021 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 2/1/2021 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 2/1/2021 Not Ready for Inspection BRIAN SULLIVAN
Deputy Drilled-In Anchors 3/5/2021 Conditional Approval BRIAN SULLIVAN
BUILDING-Rough-Frame 3/9/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 3/9/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 3/23/2021 Corrections Issued BRIAN SULLIVAN
HVAC-Rough 3/23/2021 Partial Approval BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 3/23/2021 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 4/1/2021 Partial Approval BRIAN SULLIVAN
Rough-Elec/Plmb/HVAC 4/1/2021 Partial Approval BRIAN SULLIVAN
Insulation 4/15/2021 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 4/15/2021 Approved THOMAS LOGRASSO
Shower Pan 4/15/2021 Approved THOMAS LOGRASSO
Drywall Nailing 4/27/2021 Corrections Issued BRIAN SULLIVAN
Deputy Wood Construction 4/28/2021 Conditional Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 5/5/2021 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 5/6/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 5/11/2021 Not Ready for Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 5/11/2021 Conditional Approval JOSEPH MCGARRY
Final 9/9/2022 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 10/18/2022 Approved BRIAN SULLIVAN
Drywall Nailing 10/18/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 10/18/2022 Approved BRIAN SULLIVAN
Final 10/18/2022 OK to Issue CofO BRIAN SULLIVAN
HVAC-Final 10/18/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 10/18/2022 Approved BRIAN SULLIVAN
Smoke Detectors 10/18/2022 Approved BRIAN SULLIVAN