4927 N TOWNSEND AVE 90041
Certificate Information: 4927 N TOWNSEND AVE 90041
- Application / Permit
- 20016-30000-02159
- Plan Check / Job No.
- B20WL00359
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- Alter/repair to (e) det. 2-car garage to add new partition wall for storage area and changeout (e) door
- Permit Issued
- Issued on 2/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/3/2021
Permit Application Status History
| Submitted | 1/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2020 | REZA HAGHIGHAT |
| Corrections Issued | 1/24/2020 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 1/31/2020 | KAVIAN REFAHI |
| Plan Check Approved | 1/31/2020 | KAVIAN REFAHI |
| Issued | 2/3/2021 | APPLICANT |
| Building Plans Picked Up | 3/24/2021 | APPLICANT |
| Permit Finaled | 8/2/2021 | BRIAN SULLIVAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/28/2020 | PATRICK MISCHLICH |
Contact Information
| Architect | , ; Lic. No.: C36700 | 2909 2ND ST. APT 8 SANTA MONICA, CA 90405 |
| Contractor | Eagle Rock Restoration; Lic. No.: 1025285-B | 5464 WAMEDA AVE LOS ANGELES, CA 90041 |
| Engineer | Lobnan,, Essam; Lic. No.: C78053 | PO BOX 64373 LOS ANGELES, CA 90064 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/22/2021 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/7/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/9/2021 | Partial Approval | CRAIG VAUGHAN |
| Deputy Steel/Welding | 4/13/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Other (see comments) | 4/15/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 4/20/2021 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 4/23/2021 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/11/2021 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 5/11/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/20/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 5/20/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 6/22/2021 | Approved | COREY HUPP |
| Gas Test | 6/22/2021 | Corrections Issued | COREY HUPP |
| Gas Test | 6/28/2021 | Not Ready for Inspection | COREY HUPP |
| Final | 7/27/2021 | Corrections Issued | SCOTT FINNILA |
| Smoke Detectors | 7/27/2021 | Approved | SCOTT FINNILA |
| Final | 8/2/2021 | Permit Finaled | BRIAN SULLIVAN |