13720 W HATTERAS ST 91401
Certificate Information: 13720 W HATTERAS ST 91401
- Application / Permit
- 20016-30000-02013
- Plan Check / Job No.
- B20WL00340
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO AN ADU PER STATE LAW GCS 65852.2(E)(1)(A)
- Permit Issued
- Issued on 6/18/2020
- Issuing Office
- Current Status
- CofO Corrected on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/29/2020 | TARIK SAOUD |
| Corrections Issued | 2/3/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 2/11/2020 | PARISA ZAHABI |
| Plan Check Approved | 6/5/2020 | FELIPE HERNANDEZ |
| Issued | 6/18/2020 | APPLICANT |
| Building Plans Picked Up | 11/13/2020 | APPLICANT |
| CofO in Progress | 1/5/2021 | MICHEL ABAJAN |
| CofO Issued-Status Void | 1/22/2021 | MICHAEL SMITH |
| Permit Finaled-Status Void | 1/22/2021 | MICHAEL SMITH |
| Re-Activate Permit | 12/23/2025 | RUBEN SALAS |
| Permit Finaled | 12/23/2025 | RUBEN SALAS |
| CofO Corrected | 12/23/2025 | RUBEN SALAS |
| Permit Finaled | 12/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/6/2020 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 4/8/2020 | RIDWAN HARDY |
| CPC | Cleared | 5/4/2020 | LOUIS ORTEGA |
| CPC | Cleared | 5/4/2020 | LOUIS ORTEGA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/25/2020 | Approved | MISAEL ESPARZA |
| Sewer | 8/31/2020 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 8/31/2020 | Partial Inspection | WILLIAM KUEHN |
| Excavation/Setback/Form/Re-Bar | 9/3/2020 | Approved | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/5/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 10/5/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 10/5/2020 | Partial Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 10/5/2020 | Approved | WILLIAM KUEHN |
| Insulation | 10/13/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 10/13/2020 | Approved | WILLIAM KUEHN |
| Shower Pan | 10/13/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 10/19/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 12/7/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 12/7/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 12/7/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 12/7/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/7/2020 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/7/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 12/7/2020 | Approved | JENNIFER RABUCHIN |
| Final | 12/21/2020 | Partial Approval | DANIEL ORRANTE |
| ELECTRICAL-Final | 1/5/2021 | Approved | MICHEL ABAJAN |
| Final | 1/5/2021 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 1/5/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/5/2021 | Approved | MICHEL ABAJAN |