1327 W 24TH ST 90007
Certificate Information: 1327 W 24TH ST 90007
- Application / Permit
- 20016-30000-00533
- Plan Check / Job No.
- B20WL00087
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) duplex to be converted to accessory dwelling unit.
- Permit Issued
- Issued on 8/19/2020
- Issuing Office
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | KAVIAN REFAHI |
| Corrections Issued | 2/19/2020 | KAVIAN REFAHI |
| Quality Review Completed | 2/27/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 3/10/2020 | APPLICANT |
| Applicant returned to address corrections | 7/10/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/10/2020 | KAVIAN REFAHI |
| Plan Check Approved | 8/11/2020 | KAVIAN REFAHI |
| Issued | 8/19/2020 | APPLICANT |
| Building Plans Picked Up | 8/24/2020 | APPLICANT |
| CofO in Progress | 7/25/2022 | KATHRYN BUTTERWORTH |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| "Q" conditions | Cleared | 3/2/2020 | TERRI OSBORNE |
| Construction near power lines | Cleared | 3/2/2020 | TORI CHEN |
| HPOZ | Cleared | 3/2/2020 | KATIE DEBIASE |
| ZA Case | Cleared | 3/2/2020 | KATIE DEBIASE |
| ZI | Cleared | 3/2/2020 | TERRI OSBORNE |
| Green Code | Cleared | 6/10/2020 | RICHARD GARCIA |
| Demo/Removal of Rental Units | Cleared | 7/27/2020 | EDWARD JACOBS |
| Tenant Habitability Plan | Cleared | 7/30/2020 | MICHAEL SOTO |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 5919 S CROSFT AVENUE LOS ANGELES, CA 90056 |
| Contractor | Owner-Builder | , |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 633 E 223RD ST B CARSON, CA 90745 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/16/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 9/22/2020 | Approved | DONALD CRICHLOW |
| ELECTRICAL-Rough | 9/22/2020 | Approved | DONALD CRICHLOW |
| HVAC-Rough | 9/22/2020 | Approved | DONALD CRICHLOW |
| MERV13>=Rough | 9/22/2020 | Approved | DONALD CRICHLOW |
| PLUMBING-Rough | 9/22/2020 | Approved | DONALD CRICHLOW |
| Drywall Nailing | 9/25/2020 | Approved | STUART CHAPMAN |
| Insulation | 9/25/2020 | Approved | STUART CHAPMAN |
| Final | 11/10/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 11/10/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 11/10/2020 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 11/10/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 12/23/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 12/23/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Gas Test | 12/23/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Final | 12/23/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 12/23/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 12/23/2020 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 12/23/2020 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 12/23/2020 | Approved | KATHRYN BUTTERWORTH |
| Final | 4/1/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 4/1/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Final | 7/15/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Final | 7/21/2022 | OK to Issue CofO | KATHRYN BUTTERWORTH |