134 N KILKEA DR 90048
Certificate Information: 134 N KILKEA DR 90048
- Application / Permit
- 20016-30000-00336
- Plan Check / Job No.
- B20WL00051
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) DET. GARAGE TO AN ACCESSORY DWELLING UNIT (ADU)
- Permit Issued
- Issued on 3/17/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | REZA HAGHIGHAT |
| Corrections Issued | 1/10/2020 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 3/13/2020 | PARISA ZAHABI |
| Plan Check Approved | 3/16/2020 | REZA HAGHIGHAT |
| Issued | 3/17/2020 | LADBS |
| Building Plans Picked Up | 11/20/2020 | APPLICANT |
| CofO in Progress | 9/9/2021 | EVAN COOPER |
| Permit Finaled | 9/29/2021 | KENNETH NAGLE |
| CofO Issued | 9/29/2021 | KENNETH NAGLE |
| Permit Finaled | 9/29/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Address approval | Cleared | 1/15/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 1/15/2020 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 2/21/2020 | GEORGE SUCHAND |
| Construction near power lines | Cleared | 3/17/2020 | TORI CHEN |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 5919 S CROSFT AVENUE LOS ANGELES, CA 90056 |
| Contractor | Metco Group Inc; Lic. No.: 1037705-B | 1555 SAN YSIDRO DR BEVERLY HILLS, CA 90210 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Rough | 4/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Sewer | 4/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 4/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/30/2020 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 7/30/2020 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 7/30/2020 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 7/30/2020 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 7/30/2020 | Partial Approval | EVAN COOPER |
| Deputy Drilled-In Anchors | 8/27/2020 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 8/27/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 9/29/2020 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 9/29/2020 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 9/29/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 9/29/2020 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 9/29/2020 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 9/29/2020 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 9/29/2020 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 9/29/2020 | Not Ready for Inspection | EVAN COOPER |
| Wood Frame | 9/29/2020 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 10/13/2020 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 10/13/2020 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 10/15/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 10/15/2020 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 10/15/2020 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 10/23/2020 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 10/23/2020 | Partial Approval | EVAN COOPER |
| Insulation | 10/23/2020 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 10/23/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 10/23/2020 | Approved | EVAN COOPER |
| Shower Pan | 10/23/2020 | Approved | EVAN COOPER |
| Drywall Nailing | 10/30/2020 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 10/30/2020 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 4/28/2021 | Conditional Approval | EVAN COOPER |
| Drywall Nailing | 4/28/2021 | Conditional Approval | EVAN COOPER |
| Final | 4/28/2021 | Corrections Issued | EVAN COOPER |
| Green Building Final | 4/28/2021 | Approved | EVAN COOPER |
| Green Building Rough | 4/28/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Final | 4/28/2021 | Approved | EVAN COOPER |
| METHANE-Rough | 4/28/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/28/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 5/28/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 5/28/2021 | Approved | EVAN COOPER |
| Final | 5/28/2021 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 5/28/2021 | Approved | EVAN COOPER |
| Final | 6/11/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 6/11/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 6/17/2021 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 6/17/2021 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 8/10/2021 | Approved | EVAN COOPER |
| Final | 9/9/2021 | OK to Issue CofO | EVAN COOPER |