2831 S MENLO AVE 90007
Certificate Information: 2831 S MENLO AVE 90007
- Application / Permit
- 20016-30000-00064
- Plan Check / Job No.
- B20WL00010
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) STORAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 5/18/2020
- Issuing Office
- Current Status
- CofO Issued on 12/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 2/16/2020 | ARTIN ZARUKIAN |
| Quality Review Completed | 2/19/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/20/2020 | APPLICANT |
| Green Plans Picked Up | 2/28/2020 | APPLICANT |
| Plan Check Approved | 5/8/2020 | ARTIN ZARUKIAN |
| Issued | 5/18/2020 | APPLICANT |
| CofO in Progress | 12/14/2021 | SCOTT FINNILA |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
| CofO Issued | 12/15/2021 | DEROLD HAUFF |
| Permit Finaled | 12/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/21/2020 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2020 | ELAINE LEI |
| Sewer availability | Cleared | 2/21/2020 | JEANETTE VONG |
| Specific Plan | Cleared | 2/21/2020 | PETE EYRE |
| Miscellaneous | Cleared | 2/24/2020 | SARAH GOLDMAN |
| ZA Case | Cleared | 2/24/2020 | SARAH GOLDMAN |
| City Hist. Cultural Monument | Cleared | 2/28/2020 | DANIEL MATA |
| HPOZ | Cleared | 2/28/2020 | DANIEL MATA |
| Historic monument | Cleared | 2/28/2020 | DANIEL MATA |
| Specific Plan | Cleared | 2/28/2020 | DANIEL MATA |
| ZI | Cleared | 2/28/2020 | DANIEL MATA |
| ZI | Cleared | 2/28/2020 | DANIEL MATA |
| Green Code | Cleared | 3/10/2020 | RICHARD GARCIA |
| Redevelopment Project Area | Cleared | 3/23/2020 | GRACIELA ACOSTA |
| Construction near power lines | Cleared | 4/25/2020 | RIDWAN HARDY |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 5919 S CROSFT AVENUE LOS ANGELES, CA 90056 |
| Contractor | Owner-Builder | , |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 633 E 223RD ST B CARSON, CA 90745 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/21/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 5/21/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Sewer | 5/21/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/27/2020 | Approved | KATHRYN BUTTERWORTH |
| Sewer | 5/27/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/9/2020 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/17/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/17/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/19/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/19/2020 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 6/19/2020 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 6/19/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 6/22/2020 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 6/24/2020 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 6/26/2020 | Approved | DAVID CHAN |
| Final | 7/29/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 7/29/2020 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 7/29/2020 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 7/29/2020 | Approved | KATHRYN BUTTERWORTH |
| Final | 9/27/2021 | Corrections Issued | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 9/27/2021 | SGSOV Approved | ROBERT VORHIS |
| Final | 9/29/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 11/8/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 12/14/2021 | OK to Issue CofO | SCOTT FINNILA |