2511 N MT BEACON TER 90068
Certificate Information: 2511 N MT BEACON TER 90068
- Application / Permit
- 20016-20003-29156
- Plan Check / Job No.
- B23VN12904
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPL TO 20016-20000-29156 TO REVISE THE PROPOSED FLOOR PLANS & ADD (N) 25'-7" x 26'-7" SECOND FLOOR ADDITION TO ADD (N) MASTER BEDROOM/BATH W/ A BALCONY, AND CHANGE ENGINEER OF RECORDS; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 4/9/2024
- Issuing Office
- Valley
- Current Status
- Issued on 4/9/2024
Permit Application Status History
| Submitted | 9/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2023 | SEAN SHAHMIRI |
| Corrections Issued | 10/3/2023 | SEAN SHAHMIRI |
| Quality Review Completed | 10/5/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 10/12/2023 | APPLICANT |
| Applicant returned to address corrections | 10/30/2023 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 11/8/2023 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/29/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 4/3/2024 | SEAN SHAHMIRI |
| Issued | 4/9/2024 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/2/2023 | MICHAEL TEMPLE |
| BHO/Hillside ordinance | Cleared | 10/21/2023 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 10/21/2023 | CELINA MORENO |
| Sewer availability | Cleared | 10/21/2023 | CELINA MORENO |
| Construction near power lines | Cleared | 12/12/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2024 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 3/9/2024 | KURT CORRAL |
| "D" conditions | Cleared | 3/18/2024 | TIFFANY CHEN |
| ZI | Cleared | 3/18/2024 | TIFFANY CHEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/3/2024 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 6/14/2024 | Not Ready for Inspection | ROY SPAULDING |
| Deputy Drilled-In Anchors | 7/1/2024 | Conditional Approval | JOSH MEISTER |