3058 S VINEYARD AVE 90016
Certificate Information: 3058 S VINEYARD AVE 90016
- Application / Permit
- 20016-20001-26748
- Plan Check / Job No.
- B21VN04543
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT# 20016-20000-26748 TO ADD 17'-11" x 6'-10.5" TO THE (E)SINGLE FAMILY DWELLING FOR A CLOSET AND 5'-10" x 1'-5" ADDITION TO EXPAND THE LAUNDRY ROOM. INTERIOR REMODEL TO (E)SINGLE FAMILY DWELLING TO REMOVE A BEARING WALL AT (E)KITCHEN, REFRAME (E)ROOF TO ADD NEW CELING JOISTS, CONVERT (E)CLOSET TO BATHROOM, INFILL (E)WINDOWS AND ADD NEW WINDOWS AND DOORS.
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 11/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 4/23/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 6/24/2021 | SARKIS HARABEDIAN |
| Issued | 6/25/2021 | APPLICANT |
| Building Plans Picked Up | 6/28/2021 | APPLICANT |
| CofO in Progress | 11/13/2023 | ALIZAH MAYAGOITIA |
| Permit Finaled | 11/17/2023 | DEROLD HAUFF |
| CofO Issued | 11/17/2023 | DEROLD HAUFF |
| Permit Finaled | 11/17/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/28/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2021 | CECILIO NAVARRO |
| Flood clearance | Cleared | 6/18/2021 | BRYAN GATHUKA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Manlangit,, Vicente Balingasa; Lic. No.: C75499 | 7919 SAUSALITO AVE WEST HILLS, CA 91304 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/20/2021 | Conditional Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 11/24/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/24/2022 | Partial Approval | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 6/24/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 6/24/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/25/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/25/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 8/25/2022 | Approved | STUART CHAPMAN |
| Insulation | 8/25/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 8/28/2023 | Approved | CALEB MEISTER |
| FLOOD-Elevation Certificate | 8/28/2023 | Approved | CALEB MEISTER |
| Final | 8/28/2023 | Partial Inspection | CALEB MEISTER |
| Footing/Foundation/Slab | 8/28/2023 | Approved | CALEB MEISTER |
| Green Building Final | 8/28/2023 | Approved | CALEB MEISTER |
| Smoke Detectors | 8/28/2023 | Approved | CALEB MEISTER |
| Final | 11/7/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 11/14/2023 | OK to Issue CofO | ALIZAH MAYAGOITIA |