7808 S TRUXTON AVE 90045
Certificate Information: 7808 S TRUXTON AVE 90045
- Application / Permit
- 20016-20000-33612
- Plan Check / Job No.
- B20VN16801
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18' X 32' (E) DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/10/2024
- Issuing Office
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | RAPHAEL ROSAS |
| Corrections Issued | 1/17/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/4/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 5/24/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/25/2021 | APPLICANT |
| Issued | 9/10/2024 | APPLICANT |
| CofO in Progress | 3/12/2025 | JESUS PINEDA |
| Permit Finaled | 3/13/2025 | RICHARD STEINBACH |
| CofO Issued | 3/13/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/13/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/9/2021 | CATHERINE ADROVER |
| Sewer availability | Cleared | 2/9/2021 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | CATHERINE ADROVER |
| Construction near power lines | Cleared | 4/4/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 5/13/2021 | ALEXANDER ANDREWS |
Contact Information
| Contractor | Admony Groups Corporation; Lic. No.: 1021675-B | 1932 S POINT VIEW ST LOS ANGELES, CA 90034 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 10/1/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 11/13/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Approval | BOBBY KEY |
| Gas Test | 11/13/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 11/13/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 11/13/2024 | Corrections Issued | BOBBY KEY |
| Sewer | 11/13/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 11/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Green Building Rough | 11/18/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 11/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 11/18/2024 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 11/18/2024 | Approved | TEMISTOCLES CAAL |
| Wood Frame | 11/18/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Rough | 11/22/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 11/22/2024 | Partial Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | BOBBY KEY |
| Insulation | 11/26/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 11/26/2024 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 11/26/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 12/4/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 12/6/2024 | Approved | JESUS PINEDA |
| Shower Pan | 12/6/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| Final | 2/28/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 2/28/2025 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 2/28/2025 | Approved | TEMISTOCLES CAAL |
| Final | 3/11/2025 | OK to Issue CofO | JESUS PINEDA |
| PLUMBING-Final | 3/11/2025 | Approved | JESUS PINEDA |