23530 W COLLINS ST 91367

Certificate Information: 23530 W COLLINS ST 91367

Application / Permit
20016-20000-33516
Plan Check / Job No.
B20VN16760
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20' X 20' (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER DESIGN.
Permit Issued
Issued on 2/11/2021
Issuing Office
Current Status
CofO Issued on 9/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 RAPHAEL ROSAS
Corrections Issued 1/17/2021 RAPHAEL ROSAS
Issued 2/11/2021 APPLICANT
CofO in Progress 8/10/2021 TROY SANDERS
CofO Issued 9/1/2021 JOHN JANSON
Permit Finaled 9/1/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/20/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/20/2021 ADRIAN CASTRO
Sewer availability Cleared 1/20/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 1/27/2021 BRIAN MILLER

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/22/2021 Approved TROY SANDERS
PLUMBING-Rough 3/22/2021 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 4/30/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 4/30/2021 Approved TROY SANDERS
Green Building Rough 4/30/2021 Approved TROY SANDERS
HVAC-Rough 4/30/2021 Approved TROY SANDERS
Interior/Exterior Lathing 4/30/2021 Partial Approval TROY SANDERS
PLUMBING-Rough 4/30/2021 Approved TROY SANDERS
Shower Pan 4/30/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 5/6/2021 Approved MICHAEL PELHAM
Insulation 5/6/2021 Approved JESUS PINEDA
Pre-Inspection 5/6/2021 Partial Approval JUSTIN HAWLEY
Wood Frame 5/6/2021 Partial Inspection JESUS PINEDA
Drywall Nailing 5/24/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Interior/Exterior Lathing 5/24/2021 Approved SHAVONNE ESPINOZA
Drywall Nailing 6/1/2021 Approved ALIZAH MAYAGOITIA
Sewer 6/25/2021 Approved TROY SANDERS
Final 8/10/2021 OK to Issue CofO TROY SANDERS
Green Building Final 8/10/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 8/10/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 8/10/2021 Approved TROY SANDERS