19421 W VENTURA BLVD 91356
Certificate Information: 19421 W VENTURA BLVD 91356
- Application / Permit
- 20016-20000-33504
- Plan Check / Job No.
- B20VN16746
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- REPAIR/PATCH PORTIONS OF DAMAGED ROOF. REMOVE AND REPLACE PORTIONS OF DRYWALL AND WINDOWS, AND REPAIR AND REPLACE WATER DAMAGED FLOORING AT THREE APARTMENT UNITS. REMOVE AND REPLACE DAMAGED DOORS AND PORTIONS OF DAMAGED DRYWALL AT RETAIL AND BAKERY.
- Permit Issued
- Issued on 4/14/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/26/2025
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 1/16/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/5/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| Issued | 4/14/2021 | APPLICANT |
| Permit Finaled | 12/26/2025 | BRIAN KELLY |
Permit Application Clearance Information
| Specific Plan | Cleared | 2/18/2021 | LAUREN PADICK |
Contact Information
| Contractor | Zaian Inc; Lic. No.: 1065937-B | DBA ZAIAN CONSTRUCT 18212 BATHURST STREET PORTER RANCH, CA 91326 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/20/2021 | Corrections Issued | JOHN DODGE |
| Footing/Foundation/Slab | 4/22/2022 | Corrections Issued | DANNY RODRIGUEZ |
| Final | 5/5/2022 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/5/2022 | SGSOV Not Ready | ANDREW DORSO |
| Smoke Detectors | 5/5/2022 | Not Ready for Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 6/3/2022 | Conditional Approval | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 6/10/2022 | Conditional Approval | CAMERON CHABAN |
| Footing/Foundation/Slab | 6/10/2022 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 7/8/2022 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2022 | Not Ready for Inspection | KENNETH ROBERTS |
| Wood Frame | 8/12/2022 | Not Ready for Inspection | KENNETH ROBERTS |
| Insulation | 8/22/2022 | Partial Inspection | CAMERON CHABAN |
| Wood Frame | 8/22/2022 | Partial Inspection | CAMERON CHABAN |
| Wood Frame | 8/24/2022 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 8/25/2022 | Not Ready for Inspection | CAMERON CHABAN |
| Insulation | 8/25/2022 | Approved | CAMERON CHABAN |
| Drywall Nailing | 8/26/2022 | Partial Approval | CAMERON CHABAN |
| Drywall Nailing | 9/2/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Drywall Nailing | 9/23/2022 | Partial Inspection | DANIEL VARNUM |
| Wood Frame | 10/20/2022 | Partial Approval | DANIEL VARNUM |
| Insulation | 10/25/2022 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | KENNETH ROBERTS |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Not Ready for Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 11/1/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 11/1/2022 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 11/7/2022 | Approved | ALAN NOVAK |
| Interior/Exterior Lathing | 11/7/2022 | Approved | ALAN NOVAK |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 2/7/2023 | Not Ready for Inspection | BRIAN KELLY |
| Wood Frame | 2/15/2023 | Partial Inspection | BRIAN KELLY |
| Final | 12/26/2025 | Permit Finaled | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 12/26/2025 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 12/26/2025 | Approved | BRIAN KELLY |