10109-10111 W COLWELL DR 91352

Certificate Information: 10109-10111 W COLWELL DR 91352

Application / Permit
20016-20000-33472
Plan Check / Job No.
B20VN16726
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 17' X 20'-3" ATTACHED GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
CofO Issued on 11/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2020 APPLICANT
Assigned to Plan Check Engineer 1/12/2021 JENNIFER LEE
Corrections Issued 1/13/2021 JENNIFER LEE
Plan Check Approved 3/2/2021 JENNIFER LEE
Issued 3/3/2021 APPLICANT
Building Plans Picked Up 3/5/2021 APPLICANT
CofO in Progress 9/10/2021 WILLIAM KUEHN
Permit Finaled 11/29/2021 MICHAEL SMITH
CofO Issued 11/29/2021 MICHAEL SMITH
Permit Finaled 11/29/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/20/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/20/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/21/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/3/2021 Partial Approval DAVID MATSON
PLUMBING-Rough 5/3/2021 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 5/10/2021 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 5/10/2021 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/10/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 5/12/2021 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 5/17/2021 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 5/17/2021 Not Ready for Inspection DAVID MATSON
Green Building Rough 5/17/2021 Not Ready for Inspection DAVID MATSON
MERV13>=Rough 5/17/2021 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Rough 5/21/2021 Not Ready for Inspection JOHN HAYES
Insulation 5/21/2021 Partial Approval JOHN HAYES
ELECTRICAL-Rough 6/11/2021 Approved MATTHEW NELSON
Green Building Rough 6/11/2021 Approved MATTHEW NELSON
HVAC-Rough 6/11/2021 Approved MATTHEW NELSON
MERV13>=Rough 6/11/2021 Approved MATTHEW NELSON
Insulation 6/16/2021 Approved MORRIS JACKSON
Drywall Nailing 6/21/2021 Approved MORRIS JACKSON
Interior/Exterior Lathing 6/21/2021 Approved MORRIS JACKSON
BUILDING-Rough-Frame 7/26/2021 Not Ready for Inspection JOHN HAYES
Final 7/26/2021 Corrections Issued JOHN HAYES
Green Building Final 7/26/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Final 7/26/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/26/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 7/26/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 8/10/2021 Approved WILLIAM KUEHN
Final 8/10/2021 Corrections Issued WILLIAM KUEHN
Green Building Final 8/10/2021 Not Ready for Inspection WILLIAM KUEHN
MERV13>=Final 8/10/2021 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 8/10/2021 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 8/10/2021 Approved WILLIAM KUEHN
Final 8/17/2021 Corrections Issued WILLIAM KUEHN
Green Building Final 8/17/2021 Not Ready for Inspection WILLIAM KUEHN
Final 8/19/2021 Corrections Issued WILLIAM KUEHN
Green Building Final 8/19/2021 Approved WILLIAM KUEHN
ELECTRICAL-Final 8/23/2021 Approved JENNIFER RABUCHIN
Final 8/23/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 8/23/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/23/2021 Approved JENNIFER RABUCHIN
Final 9/10/2021 OK to Issue CofO WILLIAM KUEHN