7522 S EARLDOM AVE 90293

Certificate Information: 7522 S EARLDOM AVE 90293

Application / Permit
20016-20000-33413
Plan Check / Job No.
B20VN16670
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 18'-11"X 21'-5" (E) ADETACHED STORAGE-GARAGE TO ADU. ONE CAR GARAGE IS REMAINING AS SAME USE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
CofO Issued on 12/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/12/2021 PARISA ZAHABI
Corrections Issued 1/12/2021 PARISA ZAHABI
Applicant returned to address corrections 6/28/2021 JESSE ARELLANO
Applicant returned to address corrections 8/2/2021 PARISA ZAHABI
Plan Check Approved 8/25/2021 PARISA ZAHABI
Issued 6/16/2022 APPLICANT
Building Plans Picked Up 6/22/2022 APPLICANT
CofO in Progress 12/17/2022 BOBBY KEY
Permit Finaled 12/22/2022 DANIEL ORRANTE
CofO Issued 12/22/2022 DANIEL ORRANTE
Permit Finaled 12/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/6/2021 DINAH GARIN
Sewer availability Cleared 4/6/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/13/2021 DINAH GARIN
Hydrant and Access approval Cleared 5/21/2021 KURT CORRAL
Specific Plan Cleared 6/16/2021 LAUREN PADICK
Specific Plan Cleared 7/1/2021 PETE EYRE
Grading Pre-Inspection Cleared 8/24/2021 PARISA ZAHABI

Contact Information

Contractor Faynsod Construction Company Inc; Lic. No.: 1062995-B 526 W ARBOR VITAE STREET      INGLEWOOD, CA 90301
Engineer Reith,, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Partial Approval BOBBY KEY
Underground Mechanical 7/8/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/13/2022 Conditional Approval JESUS RODRIGUEZ
Insulation 7/13/2022 Partial Approval JESUS RODRIGUEZ
Wood Frame 7/22/2022 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 7/26/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 7/26/2022 Partial Approval DAVID FEILER
HVAC-Rough 7/26/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 7/26/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 8/4/2022 Approved BOBBY KEY
ELECTRICAL-Rough 8/4/2022 Conditional Approval BOBBY KEY
Gas Test 8/4/2022 Partial Approval BOBBY KEY
HVAC-Rough 8/4/2022 Conditional Approval BOBBY KEY
METHANE-Rough 8/4/2022 Approved BOBBY KEY
PLUMBING-Rough 8/4/2022 Approved BOBBY KEY
Shower Pan 8/4/2022 Corrections Issued BOBBY KEY
Smoke Detectors 8/4/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Rough 8/11/2022 Approved BOBBY KEY
Insulation 8/11/2022 Approved BOBBY KEY
Shower Pan 8/11/2022 Approved BOBBY KEY
Drywall Nailing 8/15/2022 Approved CLAYTON GRAHAM
HVAC-Rough 8/15/2022 Approved CLAYTON GRAHAM
ELECTRICAL-Final 10/3/2022 Not Ready for Inspection BOBBY KEY
Smoke Detectors 10/3/2022 Not Ready for Inspection BOBBY KEY
Underground Mechanical 10/3/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 12/5/2022 Corrections Issued BOBBY KEY
Final 12/5/2022 Corrections Issued BOBBY KEY
HVAC-Final 12/5/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 12/5/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Final 12/16/2022 Approved BOBBY KEY
Final 12/16/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 12/16/2022 Approved BOBBY KEY
PLUMBING-Final 12/16/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Approved BOBBY KEY
Service/Power Release 12/16/2022 Approved BOBBY KEY
Smoke Detectors 12/16/2022 Approved BOBBY KEY