17218 1/2-3/4 W DEVONSHIRE ST 91325
Certificate Information: 17218 1/2-3/4 W DEVONSHIRE ST 91325
- Application / Permit
- 20016-20000-33359
- Plan Check / Job No.
- B20VN16651
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING 3-CAR GARAGE TO (N) ACCESSORY DWELLING UNIT ATTACHED TO (E) DWELLING UNIT AT REAR OF THE LOT .
- Permit Issued
- Issued on 5/21/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2020 | ALYSSA N NARCISO |
| Corrections Issued | 1/6/2021 | ALYSSA N NARCISO |
| Plan Check Approved | 5/21/2021 | ALYSSA N NARCISO |
| Issued | 5/21/2021 | APPLICANT |
| CofO in Progress | 3/17/2022 | MICHAEL TEMPLE |
| No Progress | 4/16/2022 | MICHAEL TEMPLE |
| CofO in Progress | 5/21/2022 | MICHAEL TEMPLE |
| CofO Issued | 5/21/2022 | MICHAEL SMITH |
| Permit Finaled | 5/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2021 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/25/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2021 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 3/8/2021 | MATTHEW CRAIG |
| Tenant Habitability Plan | Cleared | 4/23/2021 | RICHARD BRINSON |
| Grading Pre-Inspection | Cleared | 5/21/2021 | ALYSSA N NARCISO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/2/2021 | Partial Approval | MARK JOHNSON |
| Footing/Foundation/Slab | 9/13/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 10/5/2021 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 10/5/2021 | Approved | MARK JOHNSON |
| Sewer | 10/5/2021 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 10/6/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/7/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 10/22/2021 | Corrections Issued | MARK JOHNSON |
| Green Building Rough | 10/22/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 11/2/2021 | Approved | MARK JOHNSON |
| BUILDING-Rough-Frame | 11/23/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 11/23/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 11/23/2021 | Approved | MARK JOHNSON |
| Underground Mechanical | 11/23/2021 | Approved | MARK JOHNSON |
| Insulation | 12/1/2021 | Approved | ALAN MORELOS |
| Drywall Nailing | 12/7/2021 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 1/6/2022 | Approved | JESUS RODRIGUEZ |
| Final | 2/23/2022 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 2/23/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Not Ready | MICHAEL TEMPLE |
| Smoke Detectors | 2/23/2022 | Approved | MICHAEL TEMPLE |
| Final | 3/9/2022 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Final | 3/9/2022 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 3/9/2022 | SGSOV Approved | MICHAEL TEMPLE |
| ELECTRICAL-Final | 3/16/2022 | Approved | MICHAEL TEMPLE |
| Final | 3/16/2022 | OK to Issue CofO | MICHAEL TEMPLE |
| HVAC-Final | 3/16/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Final | 3/16/2022 | Approved | MICHAEL TEMPLE |