18829 W PRAIRIE ST 91324
Certificate Information: 18829 W PRAIRIE ST 91324
- Application / Permit
- 20016-20000-33325
- Plan Check / Job No.
- B20VN16644
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 21'-2" X 21'-7" DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- CofO Issued on 6/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 1/10/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 2/4/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 2/24/2021 | JENNIFER LEE |
| Plan Check Approved | 4/19/2021 | JENNIFER LEE |
| Issued | 4/20/2021 | APPLICANT |
| Building Plans Picked Up | 4/21/2021 | APPLICANT |
| CofO in Progress | 6/15/2023 | DAVID SCANTLIN |
| Permit Finaled | 6/30/2023 | JOHN JANSON |
| CofO Issued | 6/30/2023 | JOHN JANSON |
| Permit Finaled | 6/30/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2021 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 1/11/2021 | ABDULLAH SADOZAI |
| Construction near power lines | Cleared | 3/17/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/11/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Sewer | 1/11/2023 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/20/2023 | Partial Approval | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 3/21/2023 | Conditional Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 3/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Partial Approval | DAVID SCANTLIN |
| Pre-Inspection | 3/30/2023 | Partial Inspection | JUSTIN HAWLEY |
| Deputy Drilled-In Anchors | 4/3/2023 | Conditional Approval | HENRY KIM |
| Deputy Drilled-In Anchors | 4/3/2023 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 4/4/2023 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/4/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 4/6/2023 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 4/6/2023 | Not Ready for Inspection | SEAN HAUPT |
| Interior/Exterior Lathing | 4/6/2023 | Approved | SEAN HAUPT |
| Wood Frame | 4/6/2023 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 4/12/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 4/14/2023 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 4/14/2023 | Corrections Issued | JUSTIN HAWLEY |
| Insulation | 4/14/2023 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 4/14/2023 | Corrections Issued | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 4/19/2023 | Approved | DAVID SCANTLIN |
| Wood Frame | 4/19/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 4/21/2023 | Approved | SEAN HAUPT |
| HVAC-Rough | 4/25/2023 | Partial Inspection | JOHN KIDWELL |
| Pre-Inspection | 4/25/2023 | Partial Inspection | JUSTIN HAWLEY |
| Final | 5/31/2023 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 5/31/2023 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/31/2023 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 5/31/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Final | 6/9/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 6/9/2023 | Approved | DAVID SCANTLIN |
| HVAC-Final | 6/13/2023 | No Access for Inspection | JOHN KIDWELL |
| Final | 6/15/2023 | OK to Issue CofO | DAVID SCANTLIN |