7948-7950 N CAPISTRANO AVE 91304

Certificate Information: 7948-7950 N CAPISTRANO AVE 91304

Application / Permit
20016-20000-33304
Plan Check / Job No.
B20VN16625
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 18' X 22'-1" (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER AND CONVERT 22'-8" X 25'-10" PORTION OF (E) SFD TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.22. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/26/2021
Issuing Office
Current Status
CofO Issued on 9/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2020 APPLICANT
Assigned to Plan Check Engineer 1/8/2021 RAPHAEL ROSAS
Corrections Issued 1/9/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/26/2021 RAPHAEL ROSAS
Building Plans Picked Up 4/1/2021 APPLICANT
Issued 4/26/2021 APPLICANT
CofO in Progress 8/13/2021 DAVID STEPANYAN
Permit Finaled 9/16/2021 JOHN JANSON
CofO Issued 9/16/2021 JOHN JANSON
Permit Finaled 9/16/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/21/2021 LEE GUILBEAUX
Sewer availability Cleared 1/21/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/25/2021 LEE GUILBEAUX
Miscellaneous Cleared 3/17/2021 PABLO ESTRADA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/12/2021 Partial Inspection DAVID STEPANYAN
Deputy Drilled-In Anchors 5/17/2021 Conditional Approval STEPHANIE SWANSON
Footing/Foundation/Slab 5/25/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 5/25/2021 Corrections Issued DAVID STEPANYAN
Sewer 5/25/2021 Approved DAVID STEPANYAN
Underground Mechanical 6/1/2021 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 6/8/2021 Approved DAVID STEPANYAN
Wood Frame 6/8/2021 Corrections Issued DAVID STEPANYAN
Wood Frame 6/15/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 6/21/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 6/30/2021 Approved DAVID STEPANYAN
Gas Test 6/30/2021 Partial Approval DAVID STEPANYAN
HVAC-Rough 6/30/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 6/30/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 7/8/2021 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Approved DAVID STEPANYAN
PLUMBING-Final 7/8/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 7/13/2021 Approved DAVID STEPANYAN
Deputy Drilled-In Anchors 7/13/2021 Approved DAVID STEPANYAN
HVAC-Rough 7/13/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 7/16/2021 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 7/16/2021 Not Ready for Inspection LILIANA PORTILLO
Insulation 7/16/2021 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/16/2021 Corrections Issued LILIANA PORTILLO
Drywall Nailing 7/20/2021 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 7/20/2021 Not Ready for Inspection KRISTEN CAUSEY
Drywall Nailing 7/22/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 7/22/2021 Approved KRISTEN CAUSEY
Shower Pan 7/22/2021 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 8/9/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 8/9/2021 Corrections Issued DAVID STEPANYAN
Final 8/9/2021 Not Ready for Inspection DAVID STEPANYAN
Gas Test 8/9/2021 Corrections Issued DAVID STEPANYAN
Green Building Final 8/9/2021 Corrections Issued DAVID STEPANYAN
Green Building Rough 8/9/2021 Approved DAVID STEPANYAN
HVAC-Final 8/9/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 8/9/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 8/9/2021 Approved DAVID STEPANYAN
Final 8/10/2021 Not Ready for Inspection RONALD COWAN
Gas Test 8/10/2021 Approved RONALD COWAN
ELECTRICAL-Final 8/12/2021 Approved DAVID STEPANYAN
Final 8/12/2021 OK to Issue CofO DAVID STEPANYAN
Green Building Final 8/12/2021 Approved DAVID STEPANYAN
HVAC-Final 8/12/2021 Approved DAVID STEPANYAN
PLUMBING-Final 8/12/2021 Approved DAVID STEPANYAN