3712 N STOCKBRIDGE AVE 90032

Certificate Information: 3712 N STOCKBRIDGE AVE 90032

Application / Permit
20016-20000-33220
Plan Check / Job No.
B20VN16550
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
14' X 10' NEW ADDITION TO (E) 23' X 18' DETACHED GARAGE AND STOREROOM TO CONVERT TO ADU PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEER.
Permit Issued
Issued on 5/10/2021
Issuing Office
Current Status
CofO Issued on 3/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2020 APPLICANT
Assigned to Plan Check Engineer 1/6/2021 PARISA ZAHABI
Corrections Issued 1/6/2021 PARISA ZAHABI
Applicant returned to address corrections 3/3/2021 PARISA ZAHABI
Plan Check Approved 5/10/2021 PARISA ZAHABI
Issued 5/10/2021 APPLICANT
Building Plans Picked Up 5/12/2021 APPLICANT
CofO in Progress 1/12/2022 OSVALDO PARAMO
CofO in Progress 1/12/2022 OSVALDO PARAMO
Permit Finaled 3/2/2022 DEROLD HAUFF
CofO Issued 3/2/2022 DEROLD HAUFF
Permit Finaled 3/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/25/2021 BRIAN MILLER
Address approval Cleared 3/1/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/2/2021 WALLIE JONG
Sewer availability Cleared 3/2/2021 WALLIE JONG
Hydrant and Access approval Cleared 4/23/2021 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 5/3/2021 WALLIE JONG
Construction near power lines Cleared 5/10/2021 JEFF FOLLIN
Construction within easement Cleared 5/10/2021 JEFF FOLLIN

Contact Information

Contractor Supreme Remodeling Inc; Lic. No.: 939981-B 14545 VICTORY BLVD UNIT 401      VAN NUYS, CA 91411
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/21/2021 Corrections Issued COREY HUPP
Footing/Foundation/Slab 5/27/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 5/27/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/22/2021 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Partial Approval OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 6/29/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Partial Inspection COREY HUPP
Insulation 7/19/2021 Not Ready for Inspection COREY HUPP
Pre-Inspection 7/20/2021 Not Ready for Inspection COREY HUPP
Insulation 7/23/2021 Approved COREY HUPP
Drywall Nailing 8/2/2021 Approved COREY HUPP
Gas Test 8/2/2021 Partial Approval COREY HUPP
Interior/Exterior Lathing 8/6/2021 Partial Approval COREY HUPP
Underground Mechanical 8/6/2021 Partial Inspection COREY HUPP
Sewer 8/9/2021 Corrections Issued COREY HUPP
Sewer 8/11/2021 Approved COREY HUPP
BUILDING-Rough-Frame 10/15/2021 Approved COREY HUPP
Final 10/15/2021 Partial Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 10/15/2021 SGSOV Not Ready COREY HUPP
Smoke Detectors 10/15/2021 Approved COREY HUPP
Final 11/8/2021 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 11/8/2021 SGSOV Not Ready SCOTT FINNILA
Final 11/19/2021 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 11/19/2021 SGSOV Not Ready COREY HUPP
Final 11/30/2021 Partial Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Approved COREY HUPP
Final 12/30/2021 Corrections Issued CHRIS CHRISTENSEN
Final 1/11/2022 OK to Issue CofO OSVALDO PARAMO