4905 N NEWCASTLE AVE 91316
Certificate Information: 4905 N NEWCASTLE AVE 91316
- Application / Permit
- 20016-20000-33204
- Plan Check / Job No.
- B20VN16541
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (400 SQ FT) PER LAMC 12.22 A. 33(c) and (e)
- Permit Issued
- Issued on 2/17/2021
- Issuing Office
- Current Status
- CofO Issued on 8/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 1/8/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/17/2021 | JEROME MAGAT PALMA |
| Issued | 2/17/2021 | APPLICANT |
| CofO in Progress | 8/3/2021 | DAVID SANDOVAL |
| Permit Finaled | 8/3/2021 | MICHAEL SMITH |
| CofO Issued | 8/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/14/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 2/17/2021 | OSCAR CASTRO |
| Grading Pre-Inspection | Cleared | 2/17/2021 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/15/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/6/2021 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 4/6/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 4/6/2021 | Corrections Issued | DAVID SANDOVAL |
| Sewer | 4/6/2021 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 4/6/2021 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 4/15/2021 | Approved | DAVID SANDOVAL |
| Underground Mechanical | 4/15/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 4/22/2021 | Corrections Issued | DAVID SANDOVAL |
| Shower Pan | 4/22/2021 | Approved | DAVID SANDOVAL |
| Insulation | 4/28/2021 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/28/2021 | Approved | STEPHANIE SWANSON |
| Pre-Inspection | 4/28/2021 | Partial Inspection | RYAN SALAZAR |
| Insulation | 5/4/2021 | Approved | RYAN SALAZAR |
| Drywall Nailing | 5/13/2021 | Approved | JESUS PINEDA |
| Pre-Inspection | 5/13/2021 | Partial Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/22/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 6/22/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 6/22/2021 | Approved | DAVID SANDOVAL |
| Final | 6/30/2021 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 6/30/2021 | SGSOV Approved | DAVID SANDOVAL |
| Final | 7/9/2021 | Conditional Approval | RONALD COWAN |
| Final | 8/3/2021 | OK to Issue CofO | DAVID SANDOVAL |