4905 N NEWCASTLE AVE 91316

Certificate Information: 4905 N NEWCASTLE AVE 91316

Application / Permit
20016-20000-33204
Plan Check / Job No.
B20VN16541
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (400 SQ FT) PER LAMC 12.22 A. 33(c) and (e)
Permit Issued
Issued on 2/17/2021
Issuing Office
Current Status
CofO Issued on 8/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2020 APPLICANT
Assigned to Plan Check Engineer 1/6/2021 JEROME MAGAT PALMA
Corrections Issued 1/8/2021 JEROME MAGAT PALMA
Plan Check Approved 2/17/2021 JEROME MAGAT PALMA
Issued 2/17/2021 APPLICANT
CofO in Progress 8/3/2021 DAVID SANDOVAL
Permit Finaled 8/3/2021 MICHAEL SMITH
CofO Issued 8/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/14/2021 GABRIEL ROBLES
Sewer availability Cleared 1/14/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/15/2021 GABRIEL ROBLES
Construction near power lines Cleared 2/17/2021 OSCAR CASTRO
Grading Pre-Inspection Cleared 2/17/2021 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 4/6/2021 Approved DAVID SANDOVAL
HVAC-Rough 4/6/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 4/6/2021 Corrections Issued DAVID SANDOVAL
Sewer 4/6/2021 Approved DAVID SANDOVAL
Underground Mechanical 4/6/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 4/15/2021 Approved DAVID SANDOVAL
Underground Mechanical 4/15/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 4/22/2021 Corrections Issued DAVID SANDOVAL
Shower Pan 4/22/2021 Approved DAVID SANDOVAL
Insulation 4/28/2021 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 4/28/2021 Approved STEPHANIE SWANSON
Pre-Inspection 4/28/2021 Partial Inspection RYAN SALAZAR
Insulation 5/4/2021 Approved RYAN SALAZAR
Drywall Nailing 5/13/2021 Approved JESUS PINEDA
Pre-Inspection 5/13/2021 Partial Inspection RYAN SALAZAR
BUILDING-Rough-Frame 6/22/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 6/22/2021 Approved DAVID SANDOVAL
Final 6/30/2021 Corrections Issued DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 6/30/2021 SGSOV Approved DAVID SANDOVAL
Final 7/9/2021 Conditional Approval RONALD COWAN
Final 8/3/2021 OK to Issue CofO DAVID SANDOVAL