17453 W RAYMER ST 91325

Certificate Information: 17453 W RAYMER ST 91325

Application / Permit
20016-20000-32729
Plan Check / Job No.
B20VN16300
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 22'-4" X 24'-3" (E) DETACHED GARAGE TO ADU PER GCS 65852.2(e)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 10/6/2021
Issuing Office
Valley
Current Status
CofO Issued on 7/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 PARISA ZAHABI
Corrections Issued 2/14/2021 PARISA ZAHABI
Applicant returned to address corrections 8/16/2021 PARISA ZAHABI
Plan Check Approved 9/21/2021 PARISA ZAHABI
Building Plans Picked Up 9/22/2021 APPLICANT
Issued 10/6/2021 APPLICANT
CofO in Progress 6/16/2023 JAVIER RAMOS JR
Permit Finaled 7/19/2023 MICHAEL SMITH
CofO Issued 7/19/2023 MICHAEL SMITH
Permit Finaled 7/19/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/18/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 2/18/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 4/20/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/20/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 5/24/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 10/27/2022 Partial Approval JAVIER RAMOS JR
Pre-Inspection 10/27/2022 Approved JAVIER RAMOS JR
Sewer 10/27/2022 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 11/16/2022 Conditional Approval JAVIER RAMOS JR
Deputy Wood Construction 11/16/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 11/28/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 11/28/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/15/2022 Partial Approval JAVIER RAMOS JR
Sewer 12/21/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 1/20/2023 Approved JAVIER RAMOS JR
HVAC-Rough 1/20/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 1/20/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/25/2023 Approved JAVIER RAMOS JR
Green Building Rough 1/25/2023 Approved JAVIER RAMOS JR
Insulation 1/25/2023 Approved JAVIER RAMOS JR
Drywall Nailing 2/2/2023 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 2/2/2023 Partial Approval ARAM AVEDISIAN
Sewer 4/26/2023 Approved JAVIER RAMOS JR
Underground Mechanical 4/26/2023 Approved JAVIER RAMOS JR
Pre-Inspection 6/6/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 6/15/2023 Approved JAVIER RAMOS JR
Final 6/15/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 6/15/2023 Approved JAVIER RAMOS JR
HVAC-Final 6/15/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 6/15/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 6/15/2023 Approved JAVIER RAMOS JR
Smoke Detectors 6/15/2023 Approved JAVIER RAMOS JR