5101-5107 S PACIFIC AVE 90292
Certificate Information: 5101-5107 S PACIFIC AVE 90292
- Application / Permit
- 20016-20000-32550
- Plan Check / Job No.
- B20VN16235
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT A PORTION OF THE (E) APARTMENT INTO A (N) ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | JEFFREY TANGONAN |
| Corrections Issued | 1/2/2021 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 6/17/2021 | JEFFREY TANGONAN |
| Applicant returned to address corrections | 7/15/2021 | JEFFREY TANGONAN |
| Building Plans Picked Up | 7/19/2021 | APPLICANT |
| Applicant returned to address corrections | 8/22/2023 | WEIJIAN HUANG |
| Plan Check Approved | 9/19/2023 | DANIEL SANJUAN |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 10/26/2023 | FARHAD DADBIN |
| Permit Finaled | 11/1/2023 | DAVID TSAU |
| CofO Issued | 11/1/2023 | DAVID TSAU |
| Permit Finaled | 11/1/2023 | DAVID TSAU |
Permit Application Clearance Information
| Address approval | Cleared | 1/26/2021 | DINAH GARIN |
| Sewer availability | Cleared | 1/26/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2021 | DINAH GARIN |
| Specific Plan | Cleared | 8/30/2021 | KEVIN ARUCAN |
| Coastal Zone | Cleared | 8/18/2023 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 8/18/2023 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 8/18/2023 | LOUIS ORTEGA |
| Specific Plan | Cleared | 8/18/2023 | LOUIS ORTEGA |
| Specific Plan | Cleared | 9/18/2023 | FREDDY GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/21/2023 | Corrections Issued | AMANUEL BERHE |
| Insulation | 9/25/2023 | Approved | AMANUEL BERHE |
| Light Gage Steel Frame | 9/25/2023 | Partial Inspection | AMANUEL BERHE |
| Pre-Inspection | 9/28/2023 | Approved | FARHAD DADBIN |
| Final | 10/3/2023 | Partial Approval | FARHAD DADBIN |
| Green Building Final | 10/3/2023 | Approved | FARHAD DADBIN |
| METHANE-Final | 10/3/2023 | Approved | FARHAD DADBIN |
| Smoke Detectors | 10/3/2023 | Approved | FARHAD DADBIN |
| Final | 10/26/2023 | OK to Issue CofO | FARHAD DADBIN |