10682 N ILEX AVE 91331

Certificate Information: 10682 N ILEX AVE 91331

Application / Permit
20016-20000-32529
Plan Check / Job No.
B20VN16224
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20' X 49' (E) DETACHED GARAGE AND STORAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 3/17/2021
Issuing Office
Current Status
CofO Issued on 6/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 RAPHAEL ROSAS
Corrections Issued 12/25/2020 RAPHAEL ROSAS
Applicant returned to address corrections 2/22/2021 RAPHAEL ROSAS
Issued 3/17/2021 APPLICANT
Building Plans Picked Up 3/19/2021 APPLICANT
CofO in Progress 6/21/2022 MICHEL ABAJAN
CofO Issued 6/23/2022 MICHAEL SMITH
Permit Finaled 6/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/4/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/4/2021 GUILLERMO PETRA
Sewer availability Cleared 1/4/2021 GUILLERMO PETRA
ZI Cleared 3/4/2021 LAUREN PADICK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/8/2021 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/8/2021 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 4/19/2021 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 4/27/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/20/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/20/2021 Approved MICHEL ABAJAN
Green Building Rough 5/20/2021 Approved MICHEL ABAJAN
METHANE-Rough 5/20/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 5/20/2021 Partial Inspection MICHEL ABAJAN
Insulation 5/27/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/27/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 5/27/2021 Approved MICHEL ABAJAN
Drywall Nailing 6/4/2021 Approved KRISTEN CAUSEY
ELECTRICAL-Final 7/12/2021 Corrections Issued MICHEL ABAJAN
Final 7/12/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 7/12/2021 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 7/12/2021 Corrections Issued MICHEL ABAJAN
PLUMBING-Final 7/12/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 7/12/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/7/2022 Approved MICHEL ABAJAN
Final 4/7/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 4/7/2022 Approved MICHEL ABAJAN
HVAC-Final 4/7/2022 Approved MICHEL ABAJAN
PLUMBING-Final 4/7/2022 Approved MICHEL ABAJAN
Final 6/21/2022 OK to Issue CofO MICHEL ABAJAN