7462 N SAUSALITO AVE 91307

Certificate Information: 7462 N SAUSALITO AVE 91307

Application / Permit
20016-20000-32525
Plan Check / Job No.
B20VN16217
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20'-2" X 22'-3" (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNI PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/12/2021
Issuing Office
Current Status
CofO Issued on 3/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 RAPHAEL ROSAS
Corrections Issued 12/25/2020 RAPHAEL ROSAS
Plan Check Approved 3/20/2021 RAPHAEL ROSAS
Building Plans Picked Up 3/22/2021 APPLICANT
Issued 4/12/2021 APPLICANT
CofO in Progress 3/18/2022 STEVEN BACK
Permit Finaled 3/21/2022 JOHN JANSON
CofO Issued 3/21/2022 JOHN JANSON
Permit Finaled 3/21/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/30/2020 ADRIAN CASTRO
Sewer availability Cleared 12/30/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/31/2020 ADRIAN CASTRO
Construction near power lines Cleared 3/10/2021 RIDWAN HARDY

Contact Information

Contractor Shenon Construction; Lic. No.: 939809-B 1420 N ALTA VISTA BLVD #404      LOS ANGELES, CA 90046
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/8/2021 No Access for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 11/16/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 11/16/2021 Approved DAVID STEPANYAN
ELECTRICAL-Rough 12/16/2021 Approved PETER FOLLING
HVAC-Rough 12/16/2021 Approved PETER FOLLING
PLUMBING-Rough 12/16/2021 Approved PETER FOLLING
Wood Frame 12/16/2021 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 12/22/2021 Approved DAVID STEPANYAN
Green Building Rough 12/22/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 12/22/2021 Approved DAVID STEPANYAN
Shower Pan 12/22/2021 Approved DAVID STEPANYAN
Insulation 12/27/2021 Corrections Issued HENRY KIM
Drywall Nailing 1/5/2022 Approved SEAN HAUPT
PLUMBING-Rough 1/5/2022 Approved SEAN HAUPT
Underground Mechanical 1/5/2022 Approved SEAN HAUPT
Green Building Final 1/27/2022 Partial Approval HENRY KIM
Insulation 1/27/2022 Approved HENRY KIM
Final 3/7/2022 Corrections Issued JOHN KIDWELL
Green Building Final 3/7/2022 Approved JOHN KIDWELL
HVAC-Final 3/7/2022 Approved JOHN KIDWELL
PLUMBING-Final 3/7/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Approved JOHN KIDWELL
Smoke Detectors 3/7/2022 Approved JOHN KIDWELL
ELECTRICAL-Final 3/14/2022 Approved CHRIS CHRISTENSEN
Final 3/14/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 3/14/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 3/14/2022 Approved CHRIS CHRISTENSEN
Final 3/18/2022 OK to Issue CofO STEVEN BACK