3803 W EVANS ST 90027

Certificate Information: 3803 W EVANS ST 90027

Application / Permit
20016-20000-32368
Plan Check / Job No.
B20VN16142
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 12'-3" x 29'-2" IRR. SHAPED ADDITION (328 SF) AND NEW PATIO COVER ( 8'-5" x 20'-10", 173 SF) AT REAR OF (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL; ALL WORK PER ENGINEERING DESIGN.
Permit Issued
Issued on 10/29/2021
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 SEAN SHAHMIRI
Corrections Issued 1/10/2021 SEAN SHAHMIRI
Quality Review Completed 1/29/2021 OMID HEDAYAT
Building Plans Picked Up 2/3/2021 APPLICANT
Applicant returned to address corrections 5/5/2021 SEAN SHAHMIRI
Applicant returned to address corrections 10/14/2021 SEAN SHAHMIRI
Plan Check Approved 10/29/2021 SEAN SHAHMIRI
Issued 10/29/2021 APPLICANT
CofO in Progress 8/21/2024 ANTHONY EGSON
Permit Finaled 9/17/2024 DEROLD HAUFF
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/11/2021 BRIAN MILLER
Address approval Cleared 2/17/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 2/17/2021 RENZ SORIANO
Sewer availability Cleared 2/17/2021 RENZ SORIANO
Hydrant and Access approval Cleared 4/12/2021 MATTHEW CRAIG
Miscellaneous Cleared 4/21/2021 ARMEN SARKISIAN
Low Impact Development Cleared 9/28/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/29/2021 JEANIE LAM

Contact Information

Contractor Ahn'S Construction; Lic. No.: 1022756-B 13330 BLOOMFIELD AVENUE   SUITE 220    NORWALK, CA 90650
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/22/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 11/30/2021 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 12/15/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 12/27/2021 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 1/13/2022 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 1/25/2022 Approved JOSEPH MCGARRY
Wood Frame 1/25/2022 Partial Inspection JOSEPH MCGARRY
Deputy Drilled-In Anchors 2/9/2022 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 2/25/2022 Partial Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 2/25/2022 Not Ready for Inspection JOSEPH MCGARRY
Gas Test 2/25/2022 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 2/25/2022 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 2/25/2022 Not Ready for Inspection JOSEPH MCGARRY
Underground Mechanical 2/25/2022 Not Ready for Inspection JOSEPH MCGARRY
Deputy Wood Construction 4/4/2022 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 4/8/2022 Corrections Issued CRAIG DAVIS
Insulation 4/8/2022 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 4/8/2022 Corrections Issued CRAIG DAVIS
Wood Frame 4/8/2022 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 10/3/2022 Conditional Approval JOSEPH MCGARRY
PLUMBING-Rough 10/3/2022 Approved JOSEPH MCGARRY
Shower Pan 10/3/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 10/24/2022 Approved JOSEPH MCGARRY
HVAC-Rough 10/24/2022 Approved JOSEPH MCGARRY
Insulation 10/24/2022 Approved JOSEPH MCGARRY
Wood Frame 10/24/2022 Approved JOSEPH MCGARRY
Drywall Nailing 11/1/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 11/1/2022 Approved JOSEPH MCGARRY
Green Building Rough 11/1/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 11/1/2022 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 11/28/2022 Partial Approval RICHARD DOCKUS
Interior/Exterior Lathing 12/27/2022 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 1/13/2023 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 7/6/2023 Approved JOSEPH MCGARRY
Final 7/6/2023 Corrections Issued JOSEPH MCGARRY
Green Building Final 7/6/2023 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/6/2023 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 7/6/2023 Approved JOSEPH MCGARRY
Final 6/13/2024 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 8/20/2024 Approved ANTHONY EGSON
Final 8/20/2024 OK to Issue CofO ANTHONY EGSON
HVAC-Final 8/20/2024 Approved ANTHONY EGSON
PLUMBING-Final 8/20/2024 Approved ANTHONY EGSON