3207 S THATCHER AVE 90292
Certificate Information: 3207 S THATCHER AVE 90292
- Application / Permit
- 20016-20000-32358
- Plan Check / Job No.
- B20VN16133
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- CONVERT (E) 20'-2"x 20'-2" DETACHED 2-CAR GARAGE TO CARPORT. WORK PER ENGINEER. (SEE COMMENTS).
- Permit Issued
- Issued on 4/13/2021
- Issuing Office
- Current Status
- CofO Issued on 9/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2021 | TROY DEGUZMAN |
| Corrections Issued | 1/13/2021 | TROY DEGUZMAN |
| Quality Review Completed | 1/13/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 1/29/2021 | APPLICANT |
| Plan Check Approved | 4/7/2021 | TROY DEGUZMAN |
| Issued | 4/13/2021 | APPLICANT |
| CofO in Progress | 9/20/2022 | JESUS RODRIGUEZ |
| Permit Finaled | 9/27/2022 | DANIEL ORRANTE |
| CofO Issued | 9/27/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/27/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/9/2021 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 2/9/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 2/9/2021 | MIGUEL GAMBOA |
| Specific Plan | Cleared | 2/16/2021 | BINDU KANNAN |
| Specific Plan | Cleared | 2/16/2021 | BINDU KANNAN |
| ZI | Cleared | 2/16/2021 | BINDU KANNAN |
| ZI | Cleared | 2/16/2021 | BINDU KANNAN |
Contact Information
| Contractor | A R T E Construction & Development Inc; Lic. No.: 974107-B | 350 E ALHAMBRA RD ALHAMBRA, CA 91801 |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/25/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/10/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/22/2021 | Not Ready for Inspection | JACK MATTILLO |
| Gas Test | 6/22/2021 | Not Ready for Inspection | JACK MATTILLO |
| PLUMBING-Rough | 6/22/2021 | Not Ready for Inspection | JACK MATTILLO |
| ELECTRICAL-Rough | 6/29/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/29/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/9/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/12/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/24/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 8/26/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/26/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/13/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 11/9/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 11/22/2021 | Approved | JOHN KAYON |
| BUILDING-Rough-Frame | 12/27/2021 | Approved | ENRIQUE MIRELES |
| Final | 12/27/2021 | Corrections Issued | ENRIQUE MIRELES |
| METHANE-Final | 12/27/2021 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 12/27/2021 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/27/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 8/25/2022 | Approved | JESUS RODRIGUEZ |
| Final | 8/25/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Final | 9/19/2022 | OK to Issue CofO | JESUS RODRIGUEZ |