13831 W FOOTHILL BLVD 91342
Certificate Information: 13831 W FOOTHILL BLVD 91342
- Application / Permit
- 20016-20000-32328
- Plan Check / Job No.
- B20VN16127
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Bank
- Work Description
- INTERIOR & EXTERIOR REMODEL TO (E) BANK; REMOVE & ADD (N) CANOPY (24' X 4'-6")
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 10/8/2021
Permit Application Status History
| Submitted | 12/18/2020 | APPLICANT |
| Green Plans Picked Up | 1/4/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 1/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/19/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/19/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| Applicant returned to address corrections | 2/23/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/26/2021 | NILOOFAR MEHRAIN |
| Issued | 4/20/2021 | APPLICANT |
| Permit Finaled | 10/8/2021 | ANDREW DORSO |
Permit Application Clearance Information
| Green Code | Cleared | 2/5/2021 | MICHAEL AYERS |
| Community Plan Implem. Overlay | Cleared | 3/15/2021 | KORA MCNAUGHTON |
| ZI | Cleared | 3/15/2021 | KORA MCNAUGHTON |
| DAS Clearance | Cleared | 3/17/2021 | NILOOFAR MEHRAIN |
Contact Information
| Architect | Varda,, Richard Taylor; Lic. No.: C17764 | 19105 EAST TONTO VERDE DRIVE RIO VERDE, AZ 85263 |
| Contractor | Deb Construction L L C; Lic. No.: 372419-B | 2230 E WINSTON ROAD ANAHEIM, CA 92806 |
| Engineer | Brown,, Kelsey Felland; Lic. No.: C91203 | 2300 BERKSHIRE LANE N SUITE 200 PLYMOUTH, MN 55441 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/21/2021 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 6/28/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 6/28/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 7/1/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Structural Steel Frame | 7/1/2021 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 7/2/2021 | Partial Approval | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 7/16/2021 | Partial Inspection | ANDREW DORSO |
| Structural Steel Frame | 7/16/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 7/19/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 7/19/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 7/22/2021 | Partial Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 7/27/2021 | Partial Inspection | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2021 | Partial Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 8/12/2021 | Partial Inspection | ANDREW DORSO |
| Deputy Steel/Welding | 8/13/2021 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 8/13/2021 | Partial Inspection | ANDREW DORSO |
| Interior/Exterior Lathing | 8/13/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 8/13/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 8/16/2021 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 8/20/2021 | Partial Inspection | ANDREW DORSO |
| Drywall Nailing | 8/23/2021 | Partial Approval | RICKEY JACKSON |
| Final | 9/20/2021 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Final | 9/20/2021 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 9/20/2021 | Not Ready for Inspection | ANDREW DORSO |
| Final | 10/8/2021 | Permit Finaled | ANDREW DORSO |
| Green Building Final | 10/8/2021 | Approved | ANDREW DORSO |
| Pre-Inspection | 10/8/2021 | Approved | ANDREW DORSO |
| Smoke Detectors | 10/8/2021 | Approved | ANDREW DORSO |