12210-12212 W JUNIETTE ST 90230

Certificate Information: 12210-12212 W JUNIETTE ST 90230

Application / Permit
20016-20000-32313
Plan Check / Job No.
B20VN16120
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 18'-3" X 20'-6" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 3/16/2021
Issuing Office
Current Status
CofO Issued on 2/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2020 APPLICANT
Assigned to Plan Check Engineer 12/25/2020 JENNIFER LEE
Corrections Issued 12/28/2020 JENNIFER LEE
Plan Check Approved 3/16/2021 JENNIFER LEE
Issued 3/16/2021 APPLICANT
Building Plans Picked Up 3/17/2021 APPLICANT
CofO in Progress 10/29/2021 JOHN KAYON
Permit Finaled 2/18/2022 DANIEL ORRANTE
CofO Issued 2/18/2022 DANIEL ORRANTE
Permit Finaled 2/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/25/2021 DINAH GARIN
Sewer availability Cleared 1/25/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/26/2021 DINAH GARIN
Specific Plan Cleared 3/10/2021 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/25/2021 Corrections Issued BRENDAN LOONEY
Underground Mechanical 3/25/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 3/31/2021 Corrections Issued PIERRE VEGA
Footing/Foundation/Slab 4/20/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 6/21/2021 Partial Approval DONALD GALLAGHER
Green Building Rough 6/21/2021 Not Ready for Inspection DONALD GALLAGHER
METHANE-Rough 6/21/2021 Conditional Approval DONALD GALLAGHER
ELECTRICAL-Rough 6/30/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 6/30/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 7/7/2021 Approved ADAM ESCOTO
Deputy Wood Construction 7/9/2021 No Access for Inspection JACK MATTILLO
BUILDING-Rough-Frame 7/12/2021 Corrections Issued JOHNNY MIRANDA
Green Building Rough 7/12/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 7/12/2021 Corrections Issued JOHNNY MIRANDA
METHANE-Rough 7/12/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 8/2/2021 Approved ENRIQUE MIRELES
Green Building Rough 8/2/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Corrections Issued SHAVONNE ESPINOZA
Insulation 8/10/2021 Corrections Issued SHAVONNE ESPINOZA
Insulation 8/16/2021 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/20/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Approved ENRIQUE MIRELES
Drywall Nailing 9/1/2021 Approved JOHNNY MIRANDA
Shower Pan 9/1/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 9/8/2021 Approved ENRIQUE MIRELES
Final 9/30/2021 Corrections Issued RICHARD STEINBACH
Green Building Final 9/30/2021 Not Ready for Inspection RICHARD STEINBACH
HVAC-Final 9/30/2021 Corrections Issued RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Approved RICHARD STEINBACH
Smoke Detectors 9/30/2021 Approved RICHARD STEINBACH
ELECTRICAL-Final 10/19/2021 Corrections Issued DEANDRE HOFFMAN
HVAC-Final 10/19/2021 Corrections Issued DEANDRE HOFFMAN
PLUMBING-Final 10/19/2021 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 10/29/2021 Approved JOHN KAYON
Final 10/29/2021 OK to Issue CofO JOHN KAYON
Green Building Final 10/29/2021 Approved JOHN KAYON
HVAC-Final 10/29/2021 Approved JOHN KAYON