14016 W HAMLIN ST 91401

Certificate Information: 14016 W HAMLIN ST 91401

Application / Permit
20016-20000-32281
Plan Check / Job No.
B20VN16101
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 42' X 18' DETACHED GARAGE & HOBBY SHOP TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 12/15/2021
Issuing Office
Valley
Current Status
CofO Issued on 5/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 GURUNATH NESARAJAH
Corrections Issued 1/3/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 5/21/2021 GURUNATH NESARAJAH
Plan Check Approved 12/2/2021 GURUNATH NESARAJAH
Issued 12/15/2021 APPLICANT
Building Plans Picked Up 12/29/2021 APPLICANT
CofO in Progress 4/14/2023 RYAN SALAZAR
CofO Issued 5/7/2023 DEROLD HAUFF
Permit Finaled 5/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/9/2021 LEE GUILBEAUX
Sewer availability Cleared 4/9/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/12/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/12/2021 LEE GUILBEAUX
Construction near power lines Cleared 6/3/2021 JOHN BACON

Contact Information

Contractor Cuco Rios & Sons Construction; Lic. No.: 1015630-B PO BOX 11331      BURBANK, CA 91506
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/4/2022 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 2/11/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Not Ready for Inspection ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 2/18/2022 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 2/18/2022 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 4/28/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 4/28/2022 Approved RICHARD DOCKUS
Sewer 4/28/2022 Approved RICHARD DOCKUS
HVAC-Rough 7/11/2022 No Access for Inspection ALAN MORELOS
HVAC-Rough 7/18/2022 Approved RICHARD DOCKUS
Insulation 7/25/2022 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 7/27/2022 Approved JACK KARGODORIAN
Green Building Rough 7/27/2022 Approved JACK KARGODORIAN
Insulation 7/29/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 7/29/2022 Partial Approval ASHLEY THOMPSON
Drywall Nailing 8/3/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 8/8/2022 Approved ALAN MORELOS
ELECTRICAL-Final 1/27/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Final 1/27/2023 Not Ready for Inspection RYAN SALAZAR
Pre-Inspection 1/27/2023 Partial Inspection RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Not Ready RYAN SALAZAR
Service/Power Release 1/27/2023 Not Ready for Inspection RYAN SALAZAR
Smoke Detectors 1/27/2023 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Final 1/31/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 3/8/2023 Approved RYAN SALAZAR
Final 3/8/2023 Partial Approval RYAN SALAZAR
Green Building Final 3/8/2023 Approved RYAN SALAZAR
HVAC-Final 3/8/2023 Approved RYAN SALAZAR
PLUMBING-Final 3/8/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 3/8/2023 Not Required RYAN SALAZAR
Smoke Detectors 3/8/2023 Approved RYAN SALAZAR
Final 4/14/2023 OK to Issue CofO RYAN SALAZAR