7601 N ENCINO AVE 91325
Certificate Information: 7601 N ENCINO AVE 91325
- Application / Permit
- 20016-20000-32215
- Plan Check / Job No.
- B20VN16078
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE AND REPLACE (E) COVERED PATIO WITH 12 'X 22' BEDROOM W/ BATHROOM ADDITION AT REAR OF EX 1-STORY SFD PER ENGR DESIGN.
- Permit Issued
- Issued on 3/26/2021
- Issuing Office
- Current Status
- Issued on 3/26/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 12/27/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 3/5/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| Issued | 3/26/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/22/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/23/2021 | ADRIAN CASTRO |
| Hold | Cleared | 4/22/2021 | JASON SHEETS |
Contact Information
| Contractor | La Rocca Builders Inc; Lic. No.: 934161-B | 14320 VENTURA BLVD STE 724 SHERMAN OAKS, CA 91423 |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 2800 PLAZA DEL AMO UNIT 161 TORRANCE, CA 90503 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/29/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | Partial Approval | ARTHUR SARGSYAN |
| Insulation | 5/11/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 5/24/2021 | Corrections Issued | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 5/24/2021 | Approved | KIM BEAUCHAMP |
| Green Building Rough | 5/24/2021 | Approved | KIM BEAUCHAMP |
| PLUMBING-Rough | 5/24/2021 | Approved | KIM BEAUCHAMP |
| Insulation | 6/4/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/4/2021 | Partial Approval | JUSTIN HAWLEY |
| Drywall Nailing | 6/9/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 6/9/2021 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/16/2021 | Approved | JACK KARGODORIAN |
| Final | 7/16/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 7/16/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Gas Company | JACK KARGODORIAN |
| Smoke Detectors | 7/16/2021 | Approved | JACK KARGODORIAN |