21908-21910 W GRESHAM ST 91304

Certificate Information: 21908-21910 W GRESHAM ST 91304

Application / Permit
20016-20000-32051
Plan Check / Job No.
B20VN16002
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT (471 SQ FT) PER LAMC 12.22 A. 33(c) and (e)
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
CofO Issued on 12/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 JEROME MAGAT PALMA
Corrections Issued 1/3/2021 JEROME MAGAT PALMA
Applicant returned to address corrections 1/28/2021 JEROME MAGAT PALMA
Plan Check Approved 4/1/2021 JEROME MAGAT PALMA
Issued 4/28/2021 APPLICANT
CofO in Progress 12/21/2021 TROY SANDERS
Permit Finaled 12/22/2021 JOHN JANSON
CofO Issued 12/22/2021 JOHN JANSON
Permit Finaled 12/22/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/1/2021 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 3/1/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 3/1/2021 MARKOS PEREZ-BRAN
Grading Pre-Inspection Cleared 4/1/2021 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/19/2021 Partial Approval DAVID STEPANYAN
Pre-Inspection 7/19/2021 Partial Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 8/9/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Rough 8/9/2021 Corrections Issued DAVID STEPANYAN
Wood Frame 8/9/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 9/1/2021 Approved PETER FOLLING
ELECTRICAL-Rough 9/7/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 9/14/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Rough 9/14/2021 Corrections Issued DAVID STEPANYAN
HVAC-Rough 9/14/2021 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 9/14/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 9/20/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 9/20/2021 Approved DAVID STEPANYAN
Insulation 9/20/2021 Approved DAVID STEPANYAN
Shower Pan 9/23/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 10/26/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 10/26/2021 Not Ready for Inspection DAVID STEPANYAN
Final 11/17/2021 Corrections Issued DAVID STEPANYAN
Green Building Final 11/17/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/17/2021 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 11/17/2021 Not Ready for Inspection DAVID STEPANYAN
Final 11/29/2021 Not Ready for Inspection TROY SANDERS
Green Building Final 11/29/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 11/29/2021 Approved TROY SANDERS
Final 12/21/2021 OK to Issue CofO TROY SANDERS