10415-10417 N GERALD AVE 91344
Certificate Information: 10415-10417 N GERALD AVE 91344
- Application / Permit
- 20016-20000-31932
- Plan Check / Job No.
- B20VN15967
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 21' X 22'8" ATTACHED GARAGE TO (E) SFD INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33 (C) AND (E), ALL WORK PER WFPP
- Permit Issued
- Issued on 2/13/2021
- Issuing Office
- Current Status
- CofO Issued on 1/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | RARES BODEA |
| Corrections Issued | 12/20/2020 | RARES BODEA |
| Applicant returned to address corrections | 1/19/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 2/4/2021 | RAPHAEL ROSAS |
| Issued | 2/13/2021 | APPLICANT |
| CofO in Progress | 1/9/2023 | JAVIER RAMOS JR |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
| CofO Issued | 1/21/2023 | MICHAEL SMITH |
| Permit Finaled | 1/21/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/29/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 12/29/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/21/2021 | Conditional Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 1/10/2022 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 1/10/2022 | Partial Approval | MARK JOHNSON |
| Pre-Inspection | 1/10/2022 | Partial Inspection | MARK JOHNSON |
| Sewer | 1/10/2022 | Approved | MARK JOHNSON |
| ELECTRICAL-Rough | 6/28/2022 | Corrections Issued | JAVIER RAMOS JR |
| Wood Frame | 6/28/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/13/2022 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 7/13/2022 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 7/13/2022 | Partial Approval | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 8/5/2022 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 8/5/2022 | Approved | DEANDRE HOFFMAN |
| Green Building Rough | 8/5/2022 | Approved | DEANDRE HOFFMAN |
| HVAC-Rough | 8/5/2022 | Approved | DEANDRE HOFFMAN |
| Insulation | 8/5/2022 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Rough | 8/5/2022 | Approved | DEANDRE HOFFMAN |
| Pre-Inspection | 9/29/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/19/2022 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 12/19/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 12/19/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/29/2022 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 12/29/2022 | Approved | JAVIER RAMOS JR |