16747-16749 W INDEX ST 91344

Certificate Information: 16747-16749 W INDEX ST 91344

Application / Permit
20016-20000-31903
Plan Check / Job No.
B20VN15957
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER WFPP.
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2020 APPLICANT
Assigned to Plan Check Engineer 12/18/2020 HAYATO TSUCHIYA
Corrections Issued 12/20/2020 HAYATO TSUCHIYA
Plan Check Approved 3/8/2021 LUIS RINCON
Building Plans Picked Up 3/8/2021 APPLICANT
Issued 3/23/2021 APPLICANT
CofO in Progress 12/21/2021 TROY SANDERS
CofO Issued 9/10/2022 DANIEL ORRANTE
Permit Finaled 9/10/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/13/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/13/2021 ADRIAN CASTRO
Permit Cleared 1/13/2021 ADRIAN CASTRO
Sewer availability Cleared 1/13/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 2/8/2021 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/5/2021 Approved VINCENT HANLEY
PLUMBING-Rough 4/5/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 6/22/2021 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 6/22/2021 Not Ready for Inspection DAVID SCANTLIN
MERV13>=Rough 6/22/2021 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 6/22/2021 Not Ready for Inspection DAVID SCANTLIN
Sewer 6/22/2021 Not Ready for Inspection DAVID SCANTLIN
Gas Test 6/29/2021 Partial Approval VINCENT HANLEY
HVAC-Rough 6/29/2021 Approved VINCENT HANLEY
PLUMBING-Rough 6/29/2021 Approved VINCENT HANLEY
Sewer 7/6/2021 Approved LILIANA PORTILLO
Wood Frame 7/8/2021 Corrections Issued DAVID SCANTLIN
BUILDING-Rough-Frame 7/13/2021 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 7/13/2021 Not Ready for Inspection DAVID SCANTLIN
MERV13>=Rough 7/13/2021 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 7/13/2021 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 7/20/2021 Approved DAVID SCANTLIN
Wood Frame 7/20/2021 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Approved DAVID SCANTLIN
Insulation 8/2/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/2/2021 Approved DAVID SCANTLIN
Drywall Nailing 8/24/2021 Approved DEANDRE HOFFMAN
Green Building Rough 8/24/2021 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 11/30/2021 Approved DAVID SCANTLIN
ELECTRICAL-Final 11/30/2021 Approved DAVID SCANTLIN
Final 11/30/2021 Corrections Issued DAVID SCANTLIN
Green Building Final 11/30/2021 Approved DAVID SCANTLIN
HVAC-Final 11/30/2021 Approved DAVID SCANTLIN
MERV13>=Final 11/30/2021 Approved DAVID SCANTLIN
MERV13>=Rough 11/30/2021 Approved DAVID SCANTLIN
PLUMBING-Final 11/30/2021 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 11/30/2021 Approved DAVID SCANTLIN
Final 12/21/2021 OK to Issue CofO TROY SANDERS