2334 S MIDVALE AVE 90064

Certificate Information: 2334 S MIDVALE AVE 90064

Application / Permit
20016-20000-31833
Plan Check / Job No.
B20VN15923
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT (360 SQ FT) PER LAMC 12.22 A. 33(c) and (e)
Permit Issued
Issued on 3/4/2021
Issuing Office
Current Status
CofO Issued on 7/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 12/18/2020 JEROME MAGAT PALMA
Corrections Issued 12/20/2020 JEROME MAGAT PALMA
Plan Check Approved 1/28/2021 JEROME MAGAT PALMA
Issued 3/4/2021 APPLICANT
CofO in Progress 6/30/2022 JOHNNY MIRANDA
Permit Finaled 7/8/2022 DANIEL ORRANTE
CofO Issued 7/8/2022 DANIEL ORRANTE
Permit Finaled 7/8/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/28/2020 DINAH GARIN
Sewer availability Cleared 12/28/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/29/2020 DINAH GARIN
Specific Plan Cleared 1/6/2021 FREDDY GARCIA

Contact Information

Contractor Foundation To Roof Inc; Lic. No.: 767761-B 10800 SOUTH LA CIENEGA BL      INGLEWOOD, CA 90304
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/24/2021 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/22/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 10/18/2021 Corrections Issued JOHNNY MIRANDA
Sewer 10/18/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Corrections Issued JOHNNY MIRANDA
Rough-Elec/Plmb/HVAC 10/29/2021 Approved JOHNNY MIRANDA
Deputy Wood Construction 11/9/2021 Conditional Approval JOHNNY MIRANDA
Shower Pan 11/10/2021 Corrections Issued JOHNNY MIRANDA
Wood Frame 11/10/2021 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 11/18/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/18/2021 Approved JOHNNY MIRANDA
Shower Pan 11/18/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 11/24/2021 Approved JOHNNY MIRANDA
Insulation 12/6/2021 Approved JOHNNY MIRANDA
Drywall Nailing 12/14/2021 Approved JOHNNY MIRANDA
HVAC-Final 5/27/2022 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/9/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 6/9/2022 Approved JOHNNY MIRANDA
Final 6/9/2022 OK to Issue CofO JOHNNY MIRANDA
Green Building Final 6/9/2022 Approved JOHNNY MIRANDA
Green Building Rough 6/9/2022 Approved JOHNNY MIRANDA
PLUMBING-Final 6/9/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 6/9/2022 Approved JOHNNY MIRANDA