5895 W 2ND ST 90036

Certificate Information: 5895 W 2ND ST 90036

Application / Permit
20016-20000-31821
Plan Check / Job No.
B20VN15913
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20'-2" x 20'-4" (E) DETACHED GARAGE INTO AN (N) ACCESSORY DWELLING UNIT PER WFPP.
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2020 APPLICANT
Assigned to Plan Check Engineer 12/18/2020 ALFRED RAMIREZ
Corrections Issued 12/20/2020 ALFRED RAMIREZ
Applicant returned to address corrections 4/12/2021 ALFRED RAMIREZ
Issued 4/15/2021 APPLICANT
CofO in Progress 2/22/2022 CHRIS CHRISTENSEN
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 1/5/2021 DANIEL MATA
Address approval Cleared 1/28/2021 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 1/28/2021 JUAN ASHTON
Sewer availability Cleared 1/28/2021 JUAN ASHTON
Construction near power lines Cleared 3/25/2021 WALTER RAMIREZ

Contact Information

Contractor A R M Builders Inc; Lic. No.: 915352-B 1080 S LA CIENEGA #311      LOS ANGELES, CA 90035

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/30/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/26/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 7/7/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/7/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 7/7/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 7/7/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 7/7/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/7/2021 Approved CHRIS CHRISTENSEN
HVAC-Rough 7/23/2021 Approved CHRIS CHRISTENSEN
Insulation 7/23/2021 Conditional Approval CHRIS CHRISTENSEN
Insulation 8/18/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 8/18/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 8/23/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 8/23/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 8/23/2021 Approved CHRIS CHRISTENSEN
Sewer 9/15/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 9/15/2021 Partial Approval CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/17/2021 SGSOV Not Ready CHRIS CHRISTENSEN
ELECTRICAL-Final 10/27/2021 Approved CHRIS CHRISTENSEN
Final 10/27/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 10/27/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 10/27/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/27/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/27/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 10/27/2021 Approved CHRIS CHRISTENSEN
Final 2/18/2022 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 2/18/2022 Approved CHRIS CHRISTENSEN