2769 1/4-3/4 E MARENGO ST 90033
Certificate Information: 2769 1/4-3/4 E MARENGO ST 90033
- Application / Permit
- 20016-20000-31719
- Plan Check / Job No.
- B20VN15874
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT THE A 24'4" x 25' PORTION OF ONE OF THE UNITS INTO AN ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(C). INTERIOR PARTION WALL PER WFPP DESIGN.
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- CofO Corrected on 9/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2020 | LUIS RINCON |
| Corrections Issued | 12/23/2020 | LUIS RINCON |
| Plan Check Approved | 2/24/2021 | LUIS RINCON |
| Building Plans Picked Up | 3/4/2021 | APPLICANT |
| Issued | 3/22/2021 | APPLICANT |
| CofO in Progress | 7/6/2021 | OSVALDO PARAMO |
| CofO in Progress | 7/6/2021 | OSVALDO PARAMO |
| CofO in Progress | 7/6/2021 | OSVALDO PARAMO |
| CofO Issued-Status Void | 7/15/2021 | DEROLD HAUFF |
| Permit Finaled-Status Void | 7/15/2021 | DEROLD HAUFF |
| Re-Activate Permit | 8/4/2021 | DEROLD HAUFF |
| CofO Corrected-Status Void | 8/4/2021 | DEROLD HAUFF |
| Permit Finaled-Status Void | 8/4/2021 | DEROLD HAUFF |
| Re-Activate Permit | 8/5/2021 | DEROLD HAUFF |
| Permit Finaled | 9/1/2021 | DEROLD HAUFF |
| CofO Corrected | 9/1/2021 | DEROLD HAUFF |
| Permit Finaled | 9/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/28/2021 | CELINA MORENO |
| Sewer availability | Cleared | 1/28/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2021 | CELINA MORENO |
| Tenant Habitability Plan | Cleared | 2/5/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Procida Carl; Lic. No.: 964905-B | 13678 CAMILLA WHITTIER, CA 90601 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/26/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 3/26/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/6/2021 | Partial Approval | ROBERT VORHIS |
| ELECTRICAL-Rough | 4/6/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Rough | 4/6/2021 | Approved | ROBERT VORHIS |
| MERV13>=Rough | 4/6/2021 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 4/6/2021 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 4/19/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 4/19/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 5/10/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 5/10/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/11/2021 | Approved | OSVALDO PARAMO |
| Final | 6/11/2021 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 6/11/2021 | Approved | OSVALDO PARAMO |
| MERV13>=Final | 6/11/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/11/2021 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 6/11/2021 | Approved | OSVALDO PARAMO |
| Final | 6/23/2021 | OK to Issue CofO | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 6/23/2021 | SGSOV Approved | OSVALDO PARAMO |