9633-9635 N SWINTON AVE 91343
Certificate Information: 9633-9635 N SWINTON AVE 91343
- Application / Permit
- 20016-20000-31718
- Plan Check / Job No.
- B20VN15872
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20'-0" X 21'-6" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/5/2021
- Issuing Office
- Current Status
- CofO Issued on 9/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 12/27/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 1/20/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 2/5/2021 | JENNIFER LEE |
| Issued | 2/5/2021 | APPLICANT |
| CofO in Progress | 8/4/2021 | JACK KARGODORIAN |
| Permit Finaled | 9/9/2021 | MICHAEL SMITH |
| CofO Issued | 9/9/2021 | MICHAEL SMITH |
| Permit Finaled | 9/9/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/31/2020 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 12/31/2020 | KIRK LINKLATER |
| Sewer availability | Cleared | 12/31/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/4/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | , ; Lic. No.: C38552 | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/18/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 3/18/2021 | Corrections Issued | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 3/18/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Green Building Rough | 3/18/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 3/18/2021 | Corrections Issued | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 3/24/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 3/24/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 3/24/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 3/24/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 4/1/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 4/1/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 4/9/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 4/9/2021 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 4/9/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 6/25/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 6/25/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 6/25/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 6/25/2021 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 6/25/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2021 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 6/25/2021 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/4/2021 | Approved | JACK KARGODORIAN |
| Final | 8/4/2021 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 8/4/2021 | Approved | JACK KARGODORIAN |