9633-9635 N SWINTON AVE 91343

Certificate Information: 9633-9635 N SWINTON AVE 91343

Application / Permit
20016-20000-31718
Plan Check / Job No.
B20VN15872
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20'-0" X 21'-6" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/5/2021
Issuing Office
Current Status
CofO Issued on 9/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2020 APPLICANT
Assigned to Plan Check Engineer 12/23/2020 HAYATO TSUCHIYA
Corrections Issued 12/27/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 1/20/2021 HAYATO TSUCHIYA
Plan Check Approved 2/5/2021 JENNIFER LEE
Issued 2/5/2021 APPLICANT
CofO in Progress 8/4/2021 JACK KARGODORIAN
Permit Finaled 9/9/2021 MICHAEL SMITH
CofO Issued 9/9/2021 MICHAEL SMITH
Permit Finaled 9/9/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/31/2020 LEE GUILBEAUX
Grading Pre-Inspection Cleared 12/31/2020 KIRK LINKLATER
Sewer availability Cleared 12/31/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/4/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/4/2021 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C38552       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/18/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 3/18/2021 Corrections Issued ARTHUR SARGSYAN
ELECTRICAL-Rough 3/18/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Rough 3/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 3/18/2021 Corrections Issued ARTHUR SARGSYAN
BUILDING-Rough-Frame 3/24/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 3/24/2021 Approved ARTHUR SARGSYAN
Green Building Rough 3/24/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 3/24/2021 Approved ARTHUR SARGSYAN
Insulation 4/1/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 4/1/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 4/9/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 4/9/2021 Approved ARTHUR SARGSYAN
Shower Pan 4/9/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 6/25/2021 Not Ready for Inspection JACK KARGODORIAN
Final 6/25/2021 Corrections Issued JACK KARGODORIAN
Green Building Final 6/25/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Final 6/25/2021 Approved JACK KARGODORIAN
PLUMBING-Final 6/25/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/25/2021 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 6/25/2021 Approved JACK KARGODORIAN
ELECTRICAL-Final 8/4/2021 Approved JACK KARGODORIAN
Final 8/4/2021 OK to Issue CofO JACK KARGODORIAN
Green Building Final 8/4/2021 Approved JACK KARGODORIAN