15030 W VENTURA BLVD 91403
Certificate Information: 15030 W VENTURA BLVD 91403
- Application / Permit
- 20016-20000-31668
- Plan Check / Job No.
- B20VN15828
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- FIRE DAMAGE REPAIR TO A PORTION OF THE ROOF AND FRAMING ABOVE UNITS #24 AND 25. DAMAGE IS LESS THEN 10%. COMPLY WITH DEPARTMENT ORDER effective date 06/15/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/29/2024
Permit Application Status History
| Submitted | 12/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 12/17/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 1/6/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 1/13/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Issued | 3/25/2021 | APPLICANT |
| Permit Finaled | 2/28/2024 | BRIAN KELLY |
Permit Application Clearance Information
| Specific Plan | Cleared | 12/22/2020 | LAUREN PADICK |
| ZA Case | Cleared | 12/22/2020 | LAUREN PADICK |
Contact Information
| Contractor | Advance Construction Group Inc; Lic. No.: 612296-B | 3457 ALANA DRIVE SHERMAN OAKS, CA 91403 |
| Engineer | Ameri,, Reza; Lic. No.: C36059 | PO BOX 34979 LOS ANGELES, CA 90034 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2021 | Approved | ANDREW DORSO |
| Final | 5/15/2023 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Not Ready | ANDREW DORSO |
| Smoke Detectors | 5/15/2023 | Corrections Issued | ANDREW DORSO |
| Special/Order Compliance | 5/15/2023 | Not Ready for Inspection | STEVEN LEVITT |
| Final | 2/23/2024 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 2/23/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 2/28/2024 | Permit Finaled | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 2/28/2024 | Approved | BRIAN KELLY |