559-561 W 39TH ST 90731

Certificate Information: 559-561 W 39TH ST 90731

Application / Permit
20016-20000-31368
Plan Check / Job No.
B20VN15696
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REMODEL (E) DUPLEX TO CONVERT (2) CLOSETS TO BATHROOM, INFILL WINDOWS AND DOORS, RELOCATE ENTRY DOORS AND ADD 7'-3" X 15'-10" LATTICE ROOF PATIO AT THE FRONT. ALL WORK PER DESIGN.
Permit Issued
Issued on 5/13/2021
Issuing Office
Current Status
CofO Issued on 2/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/11/2020 RAPHAEL ROSAS
Corrections Issued 12/12/2020 RAPHAEL ROSAS
Applicant returned to address corrections 4/19/2021 RAPHAEL ROSAS
Applicant returned to address corrections 5/4/2021 RAPHAEL ROSAS
Issued 5/13/2021 APPLICANT
Building Plans Picked Up 2/4/2022 APPLICANT
CofO in Progress 2/14/2022 ANSON MAGLASANG
CofO in Progress 2/14/2022 ANSON MAGLASANG
CofO in Progress 2/18/2022 ANSON MAGLASANG
Permit Finaled 2/24/2022 DEROLD HAUFF
CofO Issued 2/24/2022 DEROLD HAUFF
Permit Finaled 2/24/2022 DEROLD HAUFF

Permit Application Clearance Information

Coastal Zone Cleared 4/20/2021 KENTON TRINH
ZI Cleared 4/27/2021 JEANALEE OBERGFELL
Grading Pre-Inspection Cleared 5/10/2021 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/24/2021 Partial Approval RICHARD STEINBACH
ELECTRICAL-Rough 6/24/2021 Approved RICHARD STEINBACH
Green Building Rough 6/24/2021 Approved RICHARD STEINBACH
METHANE-Rough 6/24/2021 Approved RICHARD STEINBACH
PLUMBING-Rough 6/24/2021 Approved RICHARD STEINBACH
Drywall Nailing 7/16/2021 Approved ANSON MAGLASANG
Interior/Exterior Lathing 7/16/2021 Partial Approval ANSON MAGLASANG
Interior/Exterior Lathing 7/22/2021 Approved JOHN KLARIN
Footing/Foundation/Slab 9/28/2021 Approved JOHN KLARIN
METHANE-Barrier 9/28/2021 Approved JOHN KLARIN
METHANE-Subgrade 9/28/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/10/2022 Approved ANSON MAGLASANG
Final 1/12/2022 Corrections Issued ANSON MAGLASANG
Green Building Final 1/12/2022 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Not Ready ANSON MAGLASANG
Smoke Detectors 1/12/2022 Not Ready for Inspection ANSON MAGLASANG
Final 2/8/2022 OK to Issue CofO ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 2/8/2022 SGSOV Approved ANSON MAGLASANG
Smoke Detectors 2/8/2022 Approved ANSON MAGLASANG