2028 1/2 S MANNING AVE 90025

Certificate Information: 2028 1/2 S MANNING AVE 90025

Application / Permit
20016-20000-31221
Plan Check / Job No.
B20VN15636
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 23' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/2/2021
Issuing Office
Current Status
CofO Issued on 8/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/11/2020 JENNIFER LEE
Corrections Issued 12/14/2020 JENNIFER LEE
Plan Check Approved 1/26/2021 JENNIFER LEE
Issued 2/2/2021 APPLICANT
CofO in Progress 6/30/2021 GERMAN RODRIGUEZ MENDOZA
CofO Issued 8/23/2021 VINCENT COTTON
Permit Finaled 8/23/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 1/13/2021 RAYMOND MUGAMBWA
Sewer availability Cleared 1/13/2021 RAYMOND MUGAMBWA
Eng Process Fee Ord 176,300 Cleared 1/14/2021 RAYMOND MUGAMBWA

Contact Information

Contractor California Building And Design Inc; Lic. No.: 950071-B 15161 MAGNOLIA BLVD SUITE D      SHERMAN OAKS, CA 91403
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/11/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 2/25/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 3/2/2021 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 3/2/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 3/2/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/2/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 3/2/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Sewer 3/3/2021 Approved GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 3/3/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 3/11/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 3/18/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/5/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 4/5/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/5/2021 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 4/5/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/5/2021 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 4/9/2021 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 4/9/2021 Approved GERMAN RODRIGUEZ MENDOZA
Shower Pan 4/9/2021 Approved GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 4/14/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/16/2021 Approved GERMAN RODRIGUEZ MENDOZA
Final 6/16/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Final 6/16/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Final 6/16/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Rough 6/16/2021 Approved GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 6/16/2021 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 6/16/2021 Approved GERMAN RODRIGUEZ MENDOZA