1443 S DURANGO AVE 90035
Certificate Information: 1443 S DURANGO AVE 90035
- Application / Permit
- 20016-20000-31167
- Plan Check / Job No.
- B20VN15607
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC: CONVERT THE (E) DETACHED GARAGE INTO A (N) 327 SQ. FT. ACCESSORY DWELLING UNIT, PER WFPP.
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2020 | SELLA BENYAMIN |
| Corrections Issued | 12/18/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 12/21/2020 | APPLICANT |
| Issued | 2/19/2021 | APPLICANT |
| CofO in Progress | 7/31/2023 | ARAM AVEDISIAN |
| Permit Finaled | 8/3/2023 | DANIEL ORRANTE |
| CofO Issued | 8/3/2023 | DANIEL ORRANTE |
| Permit Finaled | 8/3/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/4/2021 | NIKTA MOUSAVI |
| Address approval | Cleared | 1/19/2021 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2021 | NIKTA MOUSAVI |
| Hydrant and Access approval | Cleared | 2/17/2021 | JEREMY CARTER |
Contact Information
| Contractor | Best Solar Power Inc; Lic. No.: 988425-B | 17609 VENTURA BLVD #LL08 ENCINO, CA 91316 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/31/2022 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 10/27/2022 | Approved | EVAN COOPER |
| Pre-Inspection | 12/12/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 12/12/2022 | Partial Approval | JEREMY TODD |
| ELECTRICAL-Rough | 12/29/2022 | Approved | JEREMY TODD |
| Insulation | 1/10/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 3/9/2023 | Approved | JEREMY TODD |
| Green Building Rough | 3/9/2023 | Approved | JEREMY TODD |
| METHANE-Rough | 3/9/2023 | Approved | JEREMY TODD |
| Wood Frame | 3/9/2023 | Approved | JEREMY TODD |
| Insulation | 3/15/2023 | Approved | JEREMY TODD |
| Drywall Nailing | 4/11/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/11/2023 | Approved | JEREMY TODD |
| Final | 7/17/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 7/17/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 7/17/2023 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 7/17/2023 | Approved | ARAM AVEDISIAN |
| Final | 7/27/2023 | No Access for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 7/31/2023 | OK to Issue CofO | ARAM AVEDISIAN |