22631 W INGOMAR ST 91304
Certificate Information: 22631 W INGOMAR ST 91304
- Application / Permit
- 20016-20000-31163
- Plan Check / Job No.
- B20VN15605
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 21' x 21.5' GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WFPP.
- Permit Issued
- Issued on 6/30/2021
- Issuing Office
- Current Status
- CofO Issued on 7/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2020 | LUIS RINCON |
| Corrections Issued | 12/16/2020 | LUIS RINCON |
| Applicant returned to address corrections | 2/9/2021 | LUIS RINCON |
| Applicant returned to address corrections | 3/1/2021 | LUIS RINCON |
| Plan Check Approved | 3/9/2021 | LUIS RINCON |
| Building Plans Picked Up | 3/16/2021 | APPLICANT |
| Plan Check Approved | 6/29/2021 | JEFFREY TANGONAN |
| Issued | 6/30/2021 | APPLICANT |
| CofO in Progress | 4/21/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/20/2022 | JOHN JANSON |
| CofO Issued | 7/20/2022 | JOHN JANSON |
| Permit Finaled | 7/20/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/20/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/20/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/11/2021 | Corrections Issued | DAVID STEPANYAN |
| Deputy Drilled-In Anchors | 9/17/2021 | Conditional Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 9/20/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 9/24/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 9/24/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 11/8/2021 | No Access for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/8/2021 | No Access for Inspection | DAVID STEPANYAN |
| Green Building Rough | 11/8/2021 | No Access for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 11/8/2021 | No Access for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 11/8/2021 | No Access for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 11/17/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/17/2021 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2021 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 11/17/2021 | Corrections Issued | DAVID STEPANYAN |
| HVAC-Rough | 11/17/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 11/17/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/23/2021 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2021 | Partial Approval | DAVID STEPANYAN |
| HVAC-Rough | 11/23/2021 | Approved | DAVID STEPANYAN |
| Insulation | 11/23/2021 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 11/23/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/1/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 12/1/2021 | Approved | VINCENT HANLEY |
| Insulation | 12/1/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/1/2021 | Approved | VINCENT HANLEY |
| Shower Pan | 12/1/2021 | Approved | VINCENT HANLEY |
| Wood Frame | 12/1/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 12/14/2021 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 2/10/2022 | No Access for Inspection | VINCENT HANLEY |
| HVAC-Final | 2/10/2022 | No Access for Inspection | VINCENT HANLEY |
| PLUMBING-Final | 2/10/2022 | No Access for Inspection | VINCENT HANLEY |
| Final | 2/23/2022 | Corrections Issued | DAVID SCANTLIN |
| Gas Test | 2/23/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Final | 2/23/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Final | 3/1/2022 | Approved | DAVID SCANTLIN |
| Final | 3/1/2022 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 3/1/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 3/1/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/1/2022 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 3/1/2022 | Approved | DAVID SCANTLIN |
| Final | 4/20/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 4/22/2022 | Approved | CHRIS CHRISTENSEN |