17609 W CANTARA ST 91325
Certificate Information: 17609 W CANTARA ST 91325
- Application / Permit
- 20016-20000-30961
- Plan Check / Job No.
- B20VN15515
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-3" x 20'-2" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). WORK DONE PER WFPP.
- Permit Issued
- Issued on 3/18/2021
- Issuing Office
- Current Status
- CofO Issued on 9/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 12/9/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 3/18/2021 | JENNIFER LEE |
| Issued | 3/18/2021 | APPLICANT |
| Building Plans Picked Up | 3/19/2021 | APPLICANT |
| CofO in Progress | 8/19/2021 | JACK KARGODORIAN |
| Permit Finaled | 9/7/2021 | MICHAEL SMITH |
| CofO Issued | 9/7/2021 | MICHAEL SMITH |
| Permit Finaled | 9/7/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/24/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 12/24/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/24/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 2/17/2021 | JEREMY CARTER |
| Construction near power lines | Cleared | 3/4/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Gl Pro Remodeling Inc; Lic. No.: 1033036-B | 19250 HAMLIN ST #3 RESEDA, CA 91335 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/23/2021 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 5/7/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 5/19/2021 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 5/25/2021 | Partial Approval | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/3/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 6/3/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 6/3/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 6/11/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 6/11/2021 | Approved | JUSTIN HAWLEY |
| Shower Pan | 6/11/2021 | Corrections Issued | JUSTIN HAWLEY |
| Shower Pan | 6/16/2021 | Not Ready for Inspection | RYAN SALAZAR |
| Shower Pan | 6/22/2021 | Approved | RYAN SALAZAR |
| Final | 7/23/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 7/23/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 7/23/2021 | Approved | JACK KARGODORIAN |
| Final | 8/4/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 8/19/2021 | Approved | JACK KARGODORIAN |
| Final | 8/19/2021 | OK to Issue CofO | JACK KARGODORIAN |
| HVAC-Final | 8/19/2021 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 8/19/2021 | Approved | JACK KARGODORIAN |