13555 W RANGOON ST 91331

Certificate Information: 13555 W RANGOON ST 91331

Application / Permit
20016-20000-30393
Plan Check / Job No.
B20VN15252
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 6/15/2022
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2020 APPLICANT
Assigned to Plan Check Engineer 12/4/2020 ROSENDO MEDINA
Corrections Issued 12/5/2020 ROSENDO MEDINA
Applicant returned to address corrections 8/24/2021 ROSENDO MEDINA
Applicant returned to address corrections 10/19/2021 ROSENDO MEDINA
Applicant returned to address corrections 4/1/2022 ROSENDO MEDINA
Plan Check Approved 4/7/2022 ROSENDO MEDINA
Building Plans Picked Up 4/7/2022 APPLICANT
Issued 6/15/2022 APPLICANT
CofO in Progress 9/22/2025 VINCENT HANLEY
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/23/2020 ADRIAN CASTRO
Sewer availability Cleared 12/23/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/24/2020 ADRIAN CASTRO
Construction near power lines Cleared 8/3/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/11/2023 Corrections Issued GREGG CUMMINGS
Deputy Drilled-In Anchors 1/11/2023 Conditional Approval DAVID MATSON
PLUMBING-Rough 1/11/2023 Partial Approval GREGG CUMMINGS
Wood Frame 1/11/2023 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 2/9/2023 Partial Approval GREGG CUMMINGS
Sewer 2/13/2023 Approved GREGG CUMMINGS
Underground Mechanical 2/13/2023 Approved GREGG CUMMINGS
Drywall Nailing 3/10/2023 No Access for Inspection GREGG CUMMINGS
PLUMBING-Rough 4/1/2024 Approved WILLIAM WREN
Pre-Inspection 11/26/2024 Approved GREGG CUMMINGS
Pre-Inspection 12/6/2024 Corrections Issued DAVID MATSON
Pre-Inspection 2/19/2025 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 4/1/2025 Conditional Approval JUAN VALENZUELA
Wood Frame 4/7/2025 Partial Approval JACK KARGODORIAN
HVAC-Rough 4/23/2025 Approved VINCENT HANLEY
PLUMBING-Rough 4/23/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 5/15/2025 Approved DAVID MATSON
Insulation 5/15/2025 Approved DAVID MATSON
BUILDING-Rough-Frame 5/22/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Approved VINCENT HANLEY
Green Building Rough 5/22/2025 Approved VINCENT HANLEY
Shower Pan 5/22/2025 Approved VINCENT HANLEY
Drywall Nailing 6/3/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 6/3/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 8/25/2025 Corrections Issued MICHEL ABAJAN
Final 8/25/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 8/25/2025 Approved MICHEL ABAJAN
HVAC-Final 8/25/2025 Approved MICHEL ABAJAN
PLUMBING-Final 8/25/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/25/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 8/25/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/29/2025 Approved VINCENT HANLEY
Final 8/29/2025 Partial Approval VINCENT HANLEY
Final 9/22/2025 OK to Issue CofO VINCENT HANLEY