134 S WILTON DR 90004
Certificate Information: 134 S WILTON DR 90004
- Application / Permit
- 20016-20000-30386
- Plan Check / Job No.
- B20VN14700
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A).
- Permit Issued
- Issued on 3/8/2021
- Issuing Office
- Current Status
- Issued on 3/8/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2020 | TROY DEGUZMAN |
| Corrections Issued | 11/23/2020 | TROY DEGUZMAN |
| Plan Check Approved | 3/5/2021 | TROY DEGUZMAN |
| Issued | 3/8/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/2/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 12/2/2020 | THOMAS LANG |
| Sewer availability | Cleared | 12/2/2020 | THOMAS LANG |
| HPOZ | Cleared | 12/3/2020 | LAMBERT GIESSINGER |
| Green Code | Cleared | 3/5/2021 | TROY DEGUZMAN |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Outstanding Construction Inc; Lic. No.: 984746-B | 8431 MELBA AVE WEST HILLS, CA 91304 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/8/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/8/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 4/29/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/29/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Underground Mechanical | 4/29/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/13/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/19/2021 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 11/19/2021 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 11/19/2021 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 11/19/2021 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 11/24/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 12/1/2021 | Approved | MASHEL JONGERT |
| Drywall Nailing | 12/6/2021 | Approved | CRAIG DAVIS |
| Shower Pan | 12/30/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 10/25/2022 | Approved | JEFFREY MEAD |
| Final | 10/25/2022 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 10/25/2022 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Final | 10/25/2022 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 10/25/2022 | Approved | JEFFREY MEAD |