13356 W MARGATE ST 91401

Certificate Information: 13356 W MARGATE ST 91401

Application / Permit
20016-20000-30370
Plan Check / Job No.
B20VN15240
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO THE (E) KITCHEN. COMVERT ONE BATHROOM INTO TWO, REMODEL TWO BEDROOMS, LAUNDRY ROOM AND POWDER ROOM.; ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/22/2021
Issuing Office
Current Status
Permit Finaled on 8/28/2023

Permit Application Status History

Submitted 11/23/2020 APPLICANT
Assigned to Plan Check Engineer 12/7/2020 SEAN SHAHMIRI
Corrections Issued 12/7/2020 SEAN SHAHMIRI
Building Plans Picked Up 12/9/2020 APPLICANT
Plan Check Approved 5/4/2021 SEAN SHAHMIRI
Issued 5/22/2021 APPLICANT
Permit Finaled 8/25/2023 MISAEL ESPARZA

Permit Application Clearance Information

Construction near power lines Cleared 4/5/2021 RIDWAN HARDY

Contact Information

Contractor Schoon Nathan; Lic. No.: 823090-B 18225 ACRE STREET      NORTHRIDGE, CA 91325
Engineer Lobana,, Singh Maninder Pa; Lic. No.: C50989 885 PATRIOT DR #G      MOORPARK, CA 93021

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/9/2021 Partial Approval CHARLES POWELL
PLUMBING-Rough 6/18/2021 Partial Approval CHARLES POWELL
ELECTRICAL-Rough 7/2/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/2/2021 Approved ARAM AVEDISIAN
Wood Frame 7/2/2021 Partial Approval ARAM AVEDISIAN
Drywall Nailing 7/21/2021 Conditional Approval JAVIER RAMOS JR
Interior/Exterior Lathing 7/29/2021 Corrections Issued ALAN MORELOS
Insulation 8/5/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 8/5/2021 Approved ALAN MORELOS
Pre-Inspection 8/5/2021 Partial Approval ASHLEY THOMPSON
Deputy Drilled-In Anchors 11/16/2021 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 12/1/2021 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 1/26/2022 Conditional Approval MISAEL ESPARZA
Wood Frame 1/26/2022 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/10/2022 Approved MISAEL ESPARZA
ELECTRICAL-Rough 2/10/2022 Approved MISAEL ESPARZA
HVAC-Rough 2/10/2022 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 2/10/2022 Partial Approval MISAEL ESPARZA
Shower Pan 2/10/2022 Approved MISAEL ESPARZA
Drywall Nailing 3/2/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/2/2022 Approved MISAEL ESPARZA
Final 7/25/2023 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/25/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 7/25/2023 Approved MISAEL ESPARZA
Final 8/25/2023 Permit Finaled MISAEL ESPARZA