6250-6252 N AURA AVE 91335
Certificate Information: 6250-6252 N AURA AVE 91335
- Application / Permit
- 20016-20000-30349
- Plan Check / Job No.
- B20VN15227
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) ATTACHED 28' X 20' IRR.-SHAPE CARPORT TO ADU, INTERIOR REMODEL TO CONVERT (1) BATHROOM TO (2) BATHROOMS AND ADD 16' 4" X 15' 11" IRR.-SHAPE ENTRY DECK. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 2/11/2021
- Issuing Office
- Current Status
- CofO Issued on 9/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 12/6/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/27/2021 | GURUNATH NESARAJAH |
| Issued | 2/11/2021 | APPLICANT |
| CofO in Progress | 9/8/2021 | HENRY KIM |
| Permit Finaled | 9/17/2021 | JOHN JANSON |
| CofO Issued | 9/17/2021 | JOHN JANSON |
| Permit Finaled | 9/17/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 1/5/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 1/5/2021 | GUILLERMO PETRA |
| ZI | Cleared | 1/13/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 3/22/2021 | Corrections Issued | HENRY KIM |
| Underground Mechanical | 3/22/2021 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 3/30/2021 | Corrections Issued | HENRY KIM |
| Sewer | 3/30/2021 | Partial Approval | HENRY KIM |
| Footing/Foundation/Slab | 4/6/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 4/29/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2021 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 6/4/2021 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 6/4/2021 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2021 | Approved | HENRY KIM |
| Green Building Rough | 6/4/2021 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 6/4/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 6/4/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 6/10/2021 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 6/10/2021 | Approved | HENRY KIM |
| HVAC-Rough | 6/10/2021 | Approved | HENRY KIM |
| Shower Pan | 6/10/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 6/23/2021 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 6/23/2021 | Approved | STEPHANIE SWANSON |
| Insulation | 6/23/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/23/2021 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 6/28/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 6/28/2021 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/16/2021 | Corrections Issued | HENRY KIM |
| Final | 8/16/2021 | Corrections Issued | HENRY KIM |
| Green Building Final | 8/16/2021 | Approved | HENRY KIM |
| HVAC-Final | 8/16/2021 | Corrections Issued | HENRY KIM |
| PLUMBING-Final | 8/16/2021 | Corrections Issued | HENRY KIM |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Approved | HENRY KIM |
| Smoke Detectors | 8/16/2021 | Approved | HENRY KIM |
| ELECTRICAL-Final | 9/2/2021 | Approved | HENRY KIM |
| Final | 9/2/2021 | Corrections Issued | HENRY KIM |
| HVAC-Final | 9/2/2021 | Approved | HENRY KIM |
| PLUMBING-Final | 9/2/2021 | Approved | HENRY KIM |
| Final | 9/8/2021 | OK to Issue CofO | HENRY KIM |