7256 N WHITAKER AVE 91406

Certificate Information: 7256 N WHITAKER AVE 91406

Application / Permit
20016-20000-30214
Plan Check / Job No.
B20VN15171
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT IRREGULAR DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 3/1/2021
Issuing Office
Current Status
CofO Issued on 10/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2020 APPLICANT
Assigned to Plan Check Engineer 11/30/2020 LUIS RINCON
Corrections Issued 12/2/2020 LUIS RINCON
Applicant returned to address corrections 1/4/2021 LUIS RINCON
Plan Check Approved 2/7/2021 LUIS RINCON
Issued 3/1/2021 APPLICANT
CofO in Progress 7/16/2021 JACK KARGODORIAN
CofO Issued 10/19/2021 MICHAEL SMITH
Permit Finaled 10/19/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/16/2020 ADRIAN CASTRO
Sewer availability Cleared 12/16/2020 ADRIAN CASTRO
Watercourse Cleared 12/16/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/17/2020 ADRIAN CASTRO

Contact Information

Contractor My Home Builders Inc; Lic. No.: 1002927-B 20720 VENTURA BLVD #280      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 4/15/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 4/15/2021 Approved ARTHUR SARGSYAN
Green Building Rough 4/15/2021 Partial Approval ARTHUR SARGSYAN
PLUMBING-Rough 4/15/2021 Approved ARTHUR SARGSYAN
Insulation 4/23/2021 Conditional Approval MICHAEL TEMPLE
Interior/Exterior Lathing 5/12/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 5/19/2021 Approved ARTHUR SARGSYAN
Green Building Rough 5/19/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 6/28/2021 Approved JACK KARGODORIAN
ELECTRICAL-Final 6/28/2021 Not Ready for Inspection JACK KARGODORIAN
Final 6/28/2021 Corrections Issued JACK KARGODORIAN
Green Building Final 6/28/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Final 6/28/2021 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/28/2021 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 6/28/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Not Ready JACK KARGODORIAN
Final 7/16/2021 OK to Issue CofO JACK KARGODORIAN
Green Building Final 7/16/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 7/16/2021 SGSOV Approved JACK KARGODORIAN