6179 3/4 E OAK CREST WAY 90042

Certificate Information: 6179 3/4 E OAK CREST WAY 90042

Application / Permit
20016-20000-30212
Plan Check / Job No.
B20VN15170
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) IRREGULAR SHAPED 32'-7" X 36'-6" RECREATION ROOM/STORAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). NFAP13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER WFPP.
Permit Issued
Issued on 4/20/2021
Issuing Office
Current Status
CofO Issued on 6/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2020 APPLICANT
Assigned to Plan Check Engineer 12/2/2020 RAPHAEL ROSAS
Corrections Issued 12/4/2020 RAPHAEL ROSAS
Plan Check Approved 4/3/2021 RAPHAEL ROSAS
Building Plans Picked Up 4/5/2021 APPLICANT
Issued 4/20/2021 APPLICANT
CofO in Progress 3/3/2022 HAMIK HARTOUNIAN
Permit Finaled 6/28/2022 DEROLD HAUFF
CofO Issued 6/28/2022 DEROLD HAUFF
Permit Finaled 6/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/6/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 1/6/2021 WALLIE JONG
Sewer availability Cleared 1/6/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 1/28/2021 WALLIE JONG
Grading Pre-Inspection Cleared 4/3/2021 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Final 11/4/2021 Corrections Issued STUART CHAPMAN
Verify Sprinkler Sign Off 11/4/2021 Approved STUART CHAPMAN
HVAC-Rough 11/8/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Pre-Inspection 12/6/2021 Not Ready for Inspection COREY HUPP
HVAC-Final 1/10/2022 Approved CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 1/10/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/13/2022 Approved CRAIG VAUGHAN
Final 1/13/2022 Corrections Issued CRAIG VAUGHAN
Green Building Final 1/13/2022 Approved CRAIG VAUGHAN
Green Building Rough 1/13/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/13/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 1/13/2022 Corrections Issued CRAIG VAUGHAN
Final 1/28/2022 Corrections Issued HAMIK HARTOUNIAN
Smoke Detectors 1/28/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Final 2/7/2022 Not Ready for Inspection COREY HUPP
Smoke Detectors 2/7/2022 Not Ready for Inspection COREY HUPP
Final 2/24/2022 No Access for Inspection HAMIK HARTOUNIAN
Smoke Detectors 2/24/2022 No Access for Inspection HAMIK HARTOUNIAN
Pre-Inspection 3/2/2022 Partial Inspection HAMIK HARTOUNIAN
Final 3/3/2022 OK to Issue CofO HAMIK HARTOUNIAN