6179 3/4 E OAK CREST WAY 90042
Certificate Information: 6179 3/4 E OAK CREST WAY 90042
- Application / Permit
- 20016-20000-30212
- Plan Check / Job No.
- B20VN15170
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) IRREGULAR SHAPED 32'-7" X 36'-6" RECREATION ROOM/STORAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). NFAP13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/20/2021
- Issuing Office
- Current Status
- CofO Issued on 6/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2020 | RAPHAEL ROSAS |
| Corrections Issued | 12/4/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 4/3/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/5/2021 | APPLICANT |
| Issued | 4/20/2021 | APPLICANT |
| CofO in Progress | 3/3/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 6/28/2022 | DEROLD HAUFF |
| CofO Issued | 6/28/2022 | DEROLD HAUFF |
| Permit Finaled | 6/28/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2021 | WALLIE JONG |
| BHO/Hillside ordinance | Cleared | 1/6/2021 | WALLIE JONG |
| Sewer availability | Cleared | 1/6/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 4/3/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 11/4/2021 | Corrections Issued | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 11/4/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 11/8/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Pre-Inspection | 12/6/2021 | Not Ready for Inspection | COREY HUPP |
| HVAC-Final | 1/10/2022 | Approved | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 1/10/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/13/2022 | Approved | CRAIG VAUGHAN |
| Final | 1/13/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 1/13/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 1/13/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/13/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 1/13/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 1/28/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Smoke Detectors | 1/28/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 2/7/2022 | Not Ready for Inspection | COREY HUPP |
| Smoke Detectors | 2/7/2022 | Not Ready for Inspection | COREY HUPP |
| Final | 2/24/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/24/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Pre-Inspection | 3/2/2022 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 3/3/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Smoke Detectors | 3/3/2022 | Approved | HAMIK HARTOUNIAN |