19824 W VICTORY BLVD 91367
Certificate Information: 19824 W VICTORY BLVD 91367
- Application / Permit
- 20016-20000-30209
- Plan Check / Job No.
- B20VN15166
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH IRREGULAR ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.33 A33 (c) AND (d). RE-FRAME/ RE-ROOF BUILDING. WORK PER ENGINEER.
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Current Status
- CofO Corrected on 5/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | ROSENDO MEDINA |
| Corrections Issued | 12/3/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 5/4/2021 | ROSENDO MEDINA |
| Plan Check Approved | 9/8/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 9/9/2021 | APPLICANT |
| Issued | 9/17/2021 | APPLICANT |
| Re-Activate Permit | 5/18/2023 | JOHN JANSON |
| CofO in Progress | 5/18/2023 | JUSTIN HAWLEY |
| CofO Issued-Status Void | 5/18/2023 | JOHN JANSON |
| Permit Finaled-Status Void | 5/18/2023 | JOHN JANSON |
| CofO Corrected | 5/18/2023 | JOHN JANSON |
| Permit Finaled | 5/18/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/23/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 4/19/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/20/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 6/8/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/25/2021 | ANDRES COVARRUBIAS |
Contact Information
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | 20720 VENTURA BLVD #280 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/30/2021 | Corrections Issued | STEVEN BACK |
| Deputy Drilled-In Anchors | 12/15/2021 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 12/16/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 12/23/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 2/4/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 2/25/2022 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 2/25/2022 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 2/25/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 2/25/2022 | Partial Approval | STEVEN BACK |
| Sewer | 2/25/2022 | Approved | STEVEN BACK |
| Underground Mechanical | 2/25/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 4/6/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Deputy Steel/Welding | 4/6/2022 | Conditional Approval | JOHN JANSON |
| ELECTRICAL-Rough | 4/6/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 4/6/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/6/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/6/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 4/6/2022 | No Access for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/8/2022 | Approved | JEFFREY PARD |
| Rough-Elec/Plmb/HVAC | 4/8/2022 | Corrections Issued | JEFFREY PARD |
| BUILDING-Rough-Frame | 4/19/2022 | Conditional Approval | STEVEN BACK |
| ELECTRICAL-Rough | 4/19/2022 | Approved | STEVEN BACK |
| Green Building Rough | 4/19/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 4/19/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 4/19/2022 | Approved | STEVEN BACK |
| Final | 4/25/2022 | Corrections Issued | STEVEN BACK |
| Insulation | 4/25/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 5/6/2022 | Approved | STEVEN BACK |
| PLUMBING-Final | 6/10/2022 | Not Ready for Inspection | STEVEN BACK |
| Special/Order Compliance | 6/10/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 3/22/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/22/2023 | Corrections Issued | ALEXANDER HANDY |
| Final | 3/22/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 3/22/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/22/2023 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/22/2023 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/22/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 4/24/2023 | Approved | ALEXANDER HANDY |
| Final | 4/24/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 5/15/2023 | Approved | JUSTIN HAWLEY |
| Final | 5/15/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 5/15/2023 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 5/15/2023 | Approved | JUSTIN HAWLEY |
| Final | 5/18/2023 | OK to Issue CofO | JUSTIN HAWLEY |